DOC - Permit Finaled | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | PASS |
Dan Ediger
|
|
|
Work completed by the plumbing contractor
|
Water and/or Sewer | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | PART |
Bill VanDegrift
|
|
|
sewer and water test ok ok to cover, will need to inspect the sump when they figure out what the access will be.
|
Water and/or Sewer | 8/24/2018 | 8/24/2018 | 8/28/2018 | P | NR |
Bill VanDegrift
|
|
|
jason Phone #: ###-#### he was going to call Monday when he was ready but I never heard from him
|
Water and/or Sewer | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | NR |
Bill VanDegrift
|
|
|
Jason Phone #: ###-#### will haul in cover to get 36". need perssure test on the sewer.
|
Water and/or Sewer | 8/20/2018 | 8/21/2018 | 8/21/2018 | A | FAIL |
Bill VanDegrift
|
|
|
Jason Phone #: ###-#### 1) the cleanout on the building sewer is installed backwards 2) remove 2" and 4" ABS fittings and replace with PVC at tie in. ( can't mix materials) 3) use approved glue 4) pressure test PVC and water piping. 5) use two clamps at each joint on the water service piping 6) sleeve water at sewer crossing, 10 feet on each side of crossing. 7) provide a tapped fitting on the pressure sewer at the sump to blow out sewer. 8) provide 3' of cover on pressure sewer and water lines.
|
Water and/or Sewer | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PART |
Dan Ediger
|
|
|
Jason Phone #: ###-####. OK to cover water with sand or chips. Pressure test before final backfill with the waste. Use pressure pipe on the pressure sewer.
|
Other | 6/29/2018 | 6/29/2018 | 6/29/2018 | A | PASS |
Dan Ediger
|
|
|
went over the materials and fittings required to run and tie in the pressurized sewer connection.
|