Final | 12/10/2018 | 12/11/2018 | 12/11/2018 | A | PASS |
Eric Strole
|
|
|
Close out for Micron Building 37. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer
|
Storm Drains | 10/10/2018 | 10/11/2018 | 10/11/2018 | A | PART |
Eric Strole
|
|
|
Installation of 6in roof drain leaders on North East corner of Building 37. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section complete pass.
|
Storm Drains | 10/9/2018 | 10/10/2018 | 10/10/2018 | P | PART |
Eric Strole
|
|
|
Installation of 6in roof drain leaders on North East corner of Building 37. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section complete pass.
|
Roof Drains | 10/8/2018 | 10/9/2018 | 10/9/2018 | A | CANC |
Eric Strole
|
|
|
Installation of 6in roof drain leaders on North East corner of Building 37. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer
|
Roof Drains | 10/8/2018 | 10/8/2018 | 10/8/2018 | P | NR |
Eric Strole
|
|
|
Installation of 6in roof drain leaders on North East corner of Building 37. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer
|
Water and/or Sewer | 9/5/2018 | 9/6/2018 | 9/6/2018 | A | PART |
Eric Strole
|
|
|
Continuation of 6in sewer installation for building 37. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer-Test on sewer pass.
|
Water and/or Sewer | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | PART |
Eric Strole
|
|
|
Continuation of 6in sewer installation for building 37. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer-Another 56' installed.
|
Water and/or Sewer | 8/29/2018 | 8/30/2018 | 8/30/2018 | P | PART |
Eric Strole
|
|
|
Installation of 6in sewer at Bld 37. Ben Scott primary contact Phone #: ###-#### Inspection requested via web by Craig Fischer-Another 14' installed
|
Water and/or Sewer | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PART |
Eric Strole
|
|
|
Installation of 6in sewer at Bld 37. Ben Scott primary contact Phone #: ###-#### Inspection requested via web by Craig Fischer-80 ' of 6" sewer installed so far.
|
Water and/or Sewer | 8/28/2018 | 8/29/2018 | 8/29/2018 | P | PART |
Eric Strole
|
|
|
Installation of 6in sewer at Bld 37. Ben Scott primary contact Phone #: ###-#### Inspection requested via web by Craig Fischer-56' of 6' sewer installed so far.
|
Water and/or Sewer | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PART |
Eric Strole
|
|
|
nstallation of 6in sewer at Bld 37. Ben Scott primary contact Phone #: ###-#### Inspection requested via web by Craig Fischer-1st 14' of 6" sewer installed.
|
Water and/or Sewer | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | DONE |
Eric Strole
|
|
|
Installation of 6in sewer at Bld 37. Ben Scott primary contact Phone #: ###-#### Inspection requested via web by Craig Fischer-Conferance on sewer.
|
Water and/or Sewer | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Eric Strole
|
|
|
Pressure testing of 8in potable water line. Ben Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer-Test on waterline pass.
|
Water and/or Sewer | 8/3/2018 | 8/6/2018 | 8/6/2018 | A | PART |
Eric Strole
|
|
|
check on water line Ben ###-####-Waterline complete, still needs tested.
|
Water and/or Sewer | 8/2/2018 | 8/3/2018 | 8/3/2018 | P | PART |
Bill VanDegrift
|
|
|
Installation of 8in potable water line on East side of building 37. Ben Scott primary contact on site Phone #: ###-#### Inspection requested via web by Craig Fischer 100' today another 55 to go to tie in.
|
Water and/or Sewer | 8/1/2018 | 8/2/2018 | 8/2/2018 | P | PART |
Eric Strole
|
|
|
Installation of 8in potable water line on East side of building 37. Ben Scott primary contact on site Phone #: ###-#### Inspection requested via web by Craig Fischer-Tie-in to office building complete & 260' of 8" to the north installed so far.
|