Final | 12/26/2018 | 12/27/2018 | 12/27/2018 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes-Inspection done by Matt. Computer down.
|
Plumbing Rough-in | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | PASS |
Dan Ediger
|
|
|
JOB # 19899 Phone #: ###-#### Inspection requested via web by Ann Marie Reyes The ejector vent must be at least 10 feet above grade and properly supported and painted per ISPC. Will re-inspect on final
|
Plumbing Rough-in | 10/22/2018 | 10/23/2018 | 10/23/2018 | P | FAIL |
Dan Ediger
|
|
|
JOB # 19899 Phone #: ###-#### Inspection requested via web by Ann Marie Reyes Sewage ejector must be vented out the roof
|
Plumbing Rough-in | 10/19/2018 | 10/19/2018 | 10/19/2018 | P | FAIL |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes 1. Run 3/4" water to the waterless urinal per code. 2. Explain how the ejector is vented.
|
Groundwork | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PASS |
Dan Ediger
|
|
|
test was ok. Excludes sewer and water
|
Groundwork | 8/15/2018 | 8/16/2018 | 8/16/2018 | P | PEND |
Bill VanDegrift
|
|
|
JOB # 19899 Phone #: ###-#### Inspection requested via web by Ann Marie Reyes need to hear from public works before I could approve gw. set up for friday am
|