Final | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | PASS |
Eric Strole
|
|
|
GC called in so inspction can get done-Parker Phone #: ###-####
|
Final | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | PART |
Eric Strole
|
|
|
Jason Phone #: ###-####-Temp final ok.
|
Final | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | NR |
Eric Strole
|
|
|
Parker (Hunts Construction) Phone #: ###-####-Not ready
|
Groundwork | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | PASS |
Eric Strole
|
|
|
Jason Phone #: ###-####
|
Final | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | CANC |
Eric Strole
|
|
|
Jason Phone #: ###-####
|
Plumbing Rough-in | 11/23/2018 | 11/26/2018 | 11/26/2018 | A | FAIL |
Eric Strole
|
|
|
inspect floor sinks Phone #: ###-#### Inspection requested via web by Jason Williams-Need to vent flr sinks. Need to roll vent above invert. Need to use dwv fittings. Cannot use mission band from pvc to pvc. Need to test dwv.
|