Final | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Daryl Spivey
|
|
|
Brian
|
Final | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | FAIL |
Dan Ediger
|
|
|
BRIAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER 1. Provide an approved set of plans and the Occupancy sign off sheet 2. provide the water heater manual. 3. Install an 1-1/2" air gap on the 100 gal wh t&p. 4. Support and strap the t&p drain at the floor. 5.Install hangers on the flue and air combustion air to the 100 gal water heater. 6. Exopose trap primers 7. Replace the gal. water fitting with a durham drainage fitting on the hall sink. 8. Expose the urinal cleanouts.
|
Plumbing Rough-in | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Daryl Spivey
|
|
|
BRIAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Plumbing Rough-in | 11/19/2019 | 11/20/2019 | 11/20/2019 | P | NR |
Daryl Spivey
|
|
|
BRIAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Plumbing Rough-in | 10/7/2019 | 10/8/2019 | 10/8/2019 | A | PART |
Daryl Spivey
|
|
|
RILEY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER plumbing in walls ok for cover 5th floor..........ds
|
Plumbing Rough-in | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | PART |
Daryl Spivey
|
|
|
BRIAN IS THE CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER under floor waste of 5th floor R/I..........ds
|