Groundwork | 2/18/2020 | 2/18/2020 | 2/18/2020 | A | PART |
Daryl Spivey
|
|
|
Sub Rough Area A, Water main riser. Phone #: ###-#### Inspection requested via web by Preston Langdon water service and r/d and waste marked on plans.........ds
|
Groundwork | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | CANC |
Daryl Spivey
|
|
|
6" domestic water main. Phone #: ###-#### >> Inspection requested via web by Preston Langdon Inspection cancelled from web by: Preston Langdon
|
Groundwork | 2/9/2020 | 2/10/2020 | 2/10/2020 | P | PART |
Daryl Spivey
|
|
|
Sub-rough area A. Phone #: ###-#### Inspection requested via web by Preston Langdon w/v and r/d piping tested ok...........ds
|
Groundwork | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PART |
Daryl Spivey
|
|
|
Garage drain stack, Alley Phone #: ###-#### Inspection requested via web by Preston Langdon marked off all g/w done on plan...........ds
|
Groundwork | 1/20/2020 | 1/21/2020 | 1/21/2020 | P | PART |
Dan Ediger
|
|
|
Area C (NE corner) sanitary and storm drain Phone #: ###-#### Inspection requested via web by Preston Langdon. ok to cover
|
Groundwork | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PART |
Daryl Spivey
|
|
|
North East Sanitary underground. Phone #: ###-#### Inspection requested via web by Preston Langdon partial waste and R/D test ok........ds
|
Groundwork | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PART |
Dan Ediger
|
|
|
Underground bathroom group. Phone #: ###-#### Inspection requested via web by Preston Langdon se corner bath ok
|
Groundwork | 1/7/2020 | 1/7/2020 | 1/7/2020 | A | PART |
Daryl Spivey
|
|
|
Garage sanitary and water point of entry Phone #: ###-#### Inspection requested via web by Preston Langdon SS 6 in. on south east side and 1 in water line.........ds
|
Groundwork | 12/30/2019 | 12/31/2019 | 12/31/2019 | P | PART |
Daryl Spivey
|
|
|
Interceptor, Sanitary underground. Phone #: ###-#### Inspection requested via web by Preston Langdon 24 hr on SOI tested ok piping in and out ok.......ds
|
Groundwork | 12/27/2019 | 12/30/2019 | 12/30/2019 | P | PART |
Daryl Spivey
|
|
|
Garage drains, Interceptor Phone #: ###-#### Inspection requested via web by Preston Langdon garage drainage, start 24 hr on SOI trap and sanitary partial........ds
|
Groundwork | 12/19/2019 | 12/20/2019 | 12/20/2019 | A | PART |
Daryl Spivey
|
|
|
Garage drainage, SW corner. Phone #: ###-#### Inspection requested via web by Preston Langdon sanitary and garage partial ok...........ds
|
Groundwork | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | PART |
Daryl Spivey
|
|
|
Garage sump. Phone #: ###-#### Inspection requested via web by Preston Langdon partial on garage drains, sewer drain and ejector piping.......ds
|