INSP - Sewer line | 7/31/1995 | 7/31/1995 | 7/31/1995 | | DONE |
Gerry Varner
|
|
|
apx. 140' 6" sewer along south side ok, still need to grout manholes
|
INSP - Ground work | 7/27/1995 | 7/27/1995 | 7/27/1995 | P | PART |
Bill VanDegrift
|
|
|
07/27/95 330 - THIS IS FOR A CONDENSATE LINE AT 2:30 PARTIAL SEWER OK, ON TEST YET, WILL CALL WHEN READY, OK FOR PARTIAL COVE ALLOW PUMPER TRUCK ACCESS
|
INSP - Underground | 7/26/1995 | 7/26/1995 | 7/26/1995 | | NR |
Bill VanDegrift
|
|
|
/ / 330 - not ready 1:45
|
INSP - Underground | 7/26/1995 | 7/26/1995 | 7/26/1995 | | NR |
Bill VanDegrift
|
|
|
/ / 330 - not ready 1:45
|
INSP - Underground | 7/26/1995 | 7/26/1995 | 7/26/1995 | | PASS |
Bill VanDegrift
|
|
|
/ / 330 - partial sewer ok 140' 6" along west end
|
INSP - Sewer line | 7/25/1995 | 7/25/1995 | 7/25/1995 | | PASS |
Bill VanDegrift
|
|
|
07/25/95 330 - pattial sewer was done 7/24 95 for wright bros const prio permit due to a miscomunication. the section of sewer that was inspected from Bench sewer's manhole to the manhole at the west side of the buildi
|
INSP - Ground work | 7/24/1995 | 7/24/1995 | 7/24/1995 | | |
Bill VanDegrift
|
|
|
|