INSP - Conference | 8/12/1997 | 8/12/1997 | 8/12/1997 | | PASS |
Gary Ziegler
|
|
|
/ / 334 -
|
INSP - Final | 8/12/1997 | 8/12/1997 | 8/12/1997 | P | PASS |
Gary Ziegler
|
|
|
08/12/97 334 -
|
INSP - Conference | 4/18/1997 | 4/18/1997 | 4/18/1997 | | PASS |
Gary Ziegler
|
|
|
/ / 334 -
|
INSP - Framing/ Rough-in | 4/18/1997 | 4/18/1997 | 4/18/1997 | | PASS |
Gary Ziegler
|
|
|
/ / 334 -
|
INSP - Ground work | 4/18/1997 | 4/18/1997 | 4/18/1997 | | PASS |
Gary Ziegler
|
|
|
/ / 334 -
|
INSP - Plumbing Rough-in | 4/11/1997 | 4/14/1997 | 4/14/1997 | A | NR |
Gary Ziegler
|
|
|
04/14/97 334 -
|
INSP - Plumbing Rough-in | 4/10/1997 | 4/10/1997 | 4/10/1997 | A | FAIL |
Gary Ziegler
|
|
|
sent Rod correction notice , test, waste and vent and water , which I witnessed on the 04/08/97 , and that it passed but , meridians didn't ,so I had to fail his, also test, rain drain system above floor, needs to be done
|
INSP - Plumbing Rough-in | 4/8/1997 | 4/8/1997 | 4/9/1997 | P | FAIL |
Gary Ziegler
|
|
|
04/08/97 334 - meet arround 3 he said he would call you to set time meridian plumbing had corrections on groundwork, now we are in roughin s with R and D and J Bar K is the general ,need to test rain drains above floor, waste and water test ok gz,merdian plumbing needs to take care of their part before ri , gz
|