Information based on query as of Sunday, July 21, 2024.
Permit Information
Permit NumberPLM97-02792
StatusFinaled
Name HENRY FORSCHLER
Site Address 12505 W CHINDEN BLVD
Project NameBRC PHASE II
Customer Number 
ePlanReview 
Description
BOISE RESEARCH CENTER PHASE II (RETAIL BUILDING #1) sewer and water final certificate of value.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Sewer line FINAL9/2/19979/3/19979/3/1997APASS
DetailsStan Johnson
09/03/97 352 - I THINK YOU DID THIS ONE 9/2/97 CAN YOU PUT YOUR RESULTS SEWER LINE HOOKUP OK
INSP - Water lines FINAL9/3/19979/3/19979/3/1997PPASS
DetailsStan Johnson
09/03/97 352 - HOOKUP TO METER
INSP - Sewer line FINAL9/2/19279/2/19979/2/1997PPART
DetailsStan Johnson
witness deep sewer tap
INSP - Water lines8/29/19978/29/19978/29/1997PPART
DetailsStan Johnson
would like as early as possible as they need to backfill before this week-end. thanks. need hookup when meter is set