INSP - Final | 2/8/1999 | 2/9/1999 | 2/9/1999 | A | PASS |
Gerry Varner
|
|
|
02/09/99 323 - REIN\\###-#### CHRIS - FINAL OK
|
INSP - Final | 1/28/1999 | 1/29/1999 | 1/29/1999 | P | FAIL |
Gerry Varner
|
|
|
01/29/99 323 - CHRIS- ###-#### FN - INSTALL WATER METER - INSTALL DC DISPENSER
|
INSP - Final | 12/30/1998 | 12/31/1998 | 12/31/1998 | P | PART |
Gerry Varner
|
|
|
12/30/98 323 - DAN ###-#### PER GERRY VARNER FOR TEMP GAVE A TEMPERARY OCC.
|
INSP - Final | 12/28/1998 | 12/29/1998 | 12/29/1998 | P | PART |
Gerry Varner
|
|
|
12/29/98 323 - STEVE ###-#### FLOORS 1 AND 2 - 2ND FLOOR COMPLETE OK -1S GUEST ROOMS AND PUBLIC RESTROOMS ONLY OK.
|
INSP - Final | 12/28/1998 | 12/28/1998 | 12/29/1998 | P | NR |
Gary Ziegler
|
|
|
12/28/98 334 - STEVE ###-####
|
INSP - Sewer/Water lines-FINAL | 12/23/1998 | 12/23/1998 | 12/23/1998 | | PASS |
Gerry Varner
|
|
|
/ / 323 - OUTSIDE SEWER AND WATER FINAL
|
INSP - Final | 12/18/1998 | 12/18/1998 | 12/18/1998 | P | PART |
Gerry Varner
|
|
|
12/18/98 323 - steve c & r fn insp - 3RD AND 4TH FLOORS FINAL
|
INSP - Plumbing Rough-in | 11/30/1998 | 12/1/1998 | 12/1/1998 | A | PART |
Gerry Varner
|
|
|
11/30/98 323 - POOL HOUSE...DEB ###-#### - POOL HOUSE ROUGH-IN OK
|
INSP - Plumbing Rough-in | 11/10/1998 | 11/12/1998 | 11/12/1998 | A | PART |
Bill VanDegrift
|
|
|
11/12/98 330 - CONTACT STEVE ###-####--1ST FLOOR tubs
|
INSP - Plumbing Rough-in | 11/9/1998 | 11/10/1998 | 11/10/1998 | A | PART |
Bill VanDegrift
|
|
|
11/10/98 330 - PAUL ###-#### complete tubs on 2nd floor
|
INSP - Plumbing Rough-in | 11/9/1998 | 11/10/1998 | 11/10/1998 | A | PART |
Bill VanDegrift
|
|
|
11/10/98 330 - steve ###-#### early as possible please partial east side
|
INSP - Plumbing Rough-in | 11/9/1998 | 11/9/1998 | 11/9/1998 | P | FAIL |
Bill VanDegrift
|
|
|
11/09/98 330 - PAUL ###-#### R/I INSP they gotta be ready for inspection
|
INSP - Plumbing Rough-in | 11/2/1998 | 11/3/1998 | 11/9/1998 | P | PART |
Gerry Varner
|
|
|
11/02/98 323 - DEB ###-#### - PARTIAL R.I. OK
|
INSP - Plumbing Rough-in | 11/6/1998 | 11/6/1998 | 11/6/1998 | P | PART |
Jim Soden
|
|
|
11/06/98 347 - DEB ###-#### tubs 201,2,3,4,7,8,9,10,11,12 o/k---205,6 not pass
|
INSP - Plumbing Rough-in | 11/4/1998 | 11/5/1998 | 11/5/1998 | P | PART |
Gary Ziegler
|
|
|
11/05/98 334 - DEB ###-#### 2ND FLOOR
|
INSP - Plumbing Rough-in | 11/3/1998 | 11/4/1998 | 11/5/1998 | P | PART |
Gary Ziegler
|
|
|
11/05/98 334 - DEB ###-#### 3RD FLOOR
|
INSP - Plumbing Rough-in | 11/2/1998 | 11/2/1998 | 11/2/1998 | P | FAIL |
Gerry Varner
|
|
|
11/02/98 323 - DEB- ###-#### R/I INSP-4TH FLOOR - CORRECTION NEEDED - OVERFLOW GASKETS AS NEEDED AND RETEST AS REQUIRED.
|
INSP - Plumbing Rough-in | 10/29/1998 | 10/30/1998 | 10/30/1998 | P | FAIL |
Bill VanDegrift
|
|
|
10/30/98 330 - deb ###-#### for r/i insp they gotta have somethin ready
|
INSP - Plumbing Rough-in | 10/30/1998 | 10/30/1998 | 10/30/1998 | P | PART |
Bill VanDegrift
|
|
|
10/30/98 330 - ###-#### PAGER #-SOME GUY partial ri ok tubs in west 4th
|
INSP - Plumbing Rough-in | 10/28/1998 | 10/29/1998 | 10/29/1998 | A | PART |
Gerry Varner
|
|
|
10/29/98 323 - DEB- ###-#### R/I INSP PARTIAL ROUGH-IN OK
|
INSP - Plumbing Rough-in | 10/29/1998 | 10/29/1998 | 10/29/1998 | | PART |
Gerry Varner
|
|
|
10/28/98 323 - DEB- ###-#### R/I INSP - PARTIAL ROUGH-IN OK
|
INSP - Plumbing Rough-in | 10/27/1998 | 10/28/1998 | 10/28/1998 | P | FAIL |
Gerry Varner
|
|
|
10/28/98 323 - DEB ###-#### R/I INSP - CORRECTIONS NEEDED
|
INSP - Plumbing Rough-in | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PART |
Gerry Varner
|
|
|
10/27/98 323 - deb ###-#### - PARTIAL ROUGH-IN OK
|
INSP - Plumbing Rough-in | 10/22/1998 | 10/22/1998 | 10/22/1998 | P | PART |
Gerry Varner
|
|
|
10/22/98 323 - DEB ###-#### - PARTIAL ROUGH-IN OK
|
INSP - Plumbing Rough-in | 10/21/1998 | 10/21/1998 | 10/21/1998 | P | PART |
Gerry Varner
|
|
|
10/21/98 323 - deb ###-#### - PARTIAL ROUGH-IN OK
|
INSP - Plumbing Rough-in | 10/20/1998 | 10/20/1998 | 10/20/1998 | P | PART |
Gerry Varner
|
|
|
10/20/98 323 - deb ###-#### - PARTIAL ROUGH-IN OK
|
INSP - Plumbing Rough-in | 10/16/1998 | 10/19/1998 | 10/19/1998 | A | PART |
Gerry Varner
|
|
|
10/16/98 323 - DEB- ###-#### R/I - WASTE - VENTS - WATER IN NORTH WEST S FOR COVER.
|
INSP - Plumbing Rough-in | 10/16/1998 | 10/16/1998 | 10/16/1998 | P | PART |
Gerry Varner
|
|
|
10/16/98 323 - deb ###-#### - partial rough-in ok
|
INSP - Plumbing Rough-in | 10/16/1998 | 10/16/1998 | 10/16/1998 | | PART |
Gerry Varner
|
|
|
10/16/98 323 - deb ###-#### - partial rough-in ok
|
INSP - Plumbing Rough-in | 10/15/1998 | 10/15/1998 | 10/15/1998 | P | NR |
Gerry Varner
|
|
|
deb ###-#### late this afternoon
|
INSP - Plumbing Rough-in | 10/14/1998 | 10/14/1998 | 10/14/1998 | P | PART |
Gerry Varner
|
|
|
10/14/98 323 - DEB ###-#### - rough-in on bar sinks on 4th floor west
|
INSP - Plumbing Rough-in | 10/12/1998 | 10/13/1998 | 10/13/1998 | P | NR |
Gerry Varner
|
|
|
10/13/98 323 - BEV ###-#### R-IN INSP - NOT READY
|
INSP - Plumbing Rough-in | 10/2/1998 | 10/2/1998 | 10/5/1998 | P | PASS |
Gerry Varner
|
|
|
10/02/98 323 - deb ###-#### - PARTIAL ROUGH-IN OK
|
INSP - Plumbing Rough-in | 10/1/1998 | 10/1/1998 | 10/1/1998 | P | FAIL |
Gerry Varner
|
|
|
10/01/98 323 - DEB ###-#### GROUND WORK TOP OUT CORRECTIONS NEEDED
|
INSP - Plumbing Rough-in | 9/25/1998 | 9/28/1998 | 9/28/1998 | P | PART |
Gerry Varner
|
|
|
09/28/98 323 - deb ###-#### WASTE AAND VENT OF LAVS AND SINKS ON 3RD FLO
|
INSP - Plumbing Rough-in | 9/25/1998 | 9/25/1998 | 9/25/1998 | P | NR |
Gerry Varner
|
|
|
09/25/98 323 - DEB ###-#### TOP OUT - NOT READY
|
INSP - Plumbing Rough-in | 9/24/1998 | 9/24/1998 | 9/24/1998 | P | PASS |
Gerry Varner
|
|
|
09/24/98 323 - DEBBIE ###-#### CONFERENCE - CONFERENCE OK
|
INSP - Plumbing Rough-in | 9/17/1998 | 9/17/1998 | 9/17/1998 | P | PART |
Gerry Varner
|
|
|
09/17/98 323 - deb ###-#### - LAVS AND SINK WASTE AND VENTS 2ND FLOOR WE
|
INSP - Plumbing Rough-in | 9/15/1998 | 9/15/1998 | 9/15/1998 | P | PART |
Gerry Varner
|
|
|
09/15/98 323 - DEB ###-#### PER JERRY V WILL DO TODAY - WASTE AND VENTS AND SINKS ON 1ST AND 2ND FLOOR EAST END OK
|
INSP - Plumbing Rough-in | 9/14/1998 | 9/14/1998 | 9/14/1998 | P | PASS |
Gerry Varner
|
|
|
09/14/98 323 - DEB ###-#### LATE THIS AFTERNOON - rough-in ok
|
INSP - Final | 9/10/1998 | 9/11/1998 | 9/13/1998 | P | NR |
Gerry Varner
|
|
|
09/11/98 323 - deb ###-#### optical dept NOT THE RIGHT ADDRESS FOR THIS JOB
|
INSP - Plumbing Rough-in | 9/10/1998 | 9/11/1998 | 9/11/1998 | A | PART |
Gerry Varner
|
|
|
09/11/98 323 - deb ###-#### - LOWER WEST 8 UNITS WASTE AND VENTS ONLY
|
INSP - Plumbing Rough-in | 9/10/1998 | 9/10/1998 | 9/11/1998 | P | NR |
Gerry Varner
|
|
|
09/10/98 323 - DEB ###-#### - NOT READY FOR INSPECTION
|
INSP - Plumbing Rough-in | 9/2/1998 | 9/2/1998 | 9/2/1998 | P | PASS |
Gerry Varner
|
|
|
09/02/98 323 - Scheduled by Hello!. Contact phone is [3638560]. OUTSIDE WATER LINE OK
|
INSP - Plumbing Rough-in | 8/14/1998 | 8/14/1998 | 8/14/1998 | P | PASS |
Gerry Varner
|
|
|
08/14/98 323 - water and gas amy ###-#### - WATER LINE OK
|
INSP - Plumbing Rough-in | 8/13/1998 | 8/14/1998 | 8/14/1998 | A | NR |
Gerry Varner
|
|
|
08/14/98 323 - UNDERGROUND GAS (?) AND WATER AMY ###-#### NOT READY FOR INSPECTION
|
INSP - Plumbing Rough-in | 6/22/1998 | 6/23/1998 | 6/24/1998 | P | PART |
Gerry Varner
|
|
|
06/23/98 323 - Scheduled by Hello!. Contact phone is [3638560]. PARTIAL GROUND WORK OK
|
INSP - Plumbing Rough-in | 6/15/1998 | 6/16/1998 | 6/16/1998 | A | PASS |
Gerry Varner
|
|
|
06/16/98 323 - Scheduled by Hello!. Contact phone is [3627785]. PARTIAL WATER LINE OK
|
INSP - Conference | 5/21/1998 | 5/21/1998 | 5/21/1998 | | PASS |
Gary Ziegler
|
|
|
/ / 334 -
|
INSP - Plumbing Rough-in | 5/19/1998 | 5/20/1998 | 5/21/1998 | P | PASS |
Gary Ziegler
|
|
|
05/20/98 334 - early p.m. if possible/ underground/ ###-####
|
INSP - Plumbing Rough-in | 1/8/1999 | 1/6/1998 | 1/6/1998 | | FAIL |
|
|
|
Issued citations to 4 individuals witnessed doing plumbing work on site in violation of Boise City Ord. 4-1-15F. (working without juorneyman supervision) See general report #plm98-1307.
|