Permit Information
Permit NumberPLM99-03833
StatusFinaled
Name DE BEST PLUMBING INC
Site Address 1650 W STATE ST
Project Name 
Customer Number99-141
ePlanReview 
Description
11/12/99-Albertson's Store #101- hot and cold domestic water, waste and vents, plumbing fixtures, etc.-$70,000.00-initial cert. of value.mps 4/9-final cert 119,111.00 lh
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Water and/or Sewer1/24/20011/24/20011/24/2001PPASS
DetailsGary Ziegler
Added by Inspector: 334 On 1/24/2001 2:00:34 PM
Final7/7/20007/10/20007/10/2000APASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 07/07/2000 at 14:29:06. Contact: ###-####.
Final6/29/20006/29/20006/29/2000PFAIL
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 06/29/2000 at 11:10:05. Contact: ###-####.
Groundwork5/24/20005/25/20005/25/2000APASS
DetailsGary Ziegler
Kim ###-#### at 4:30 am
Groundwork5/19/20005/22/20005/22/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 05/19/2000 at 16:18:12. Contact: ###-####.
Plumbing Rough-in5/12/20005/12/20005/12/2000PPART
DetailsGary Ziegler
per gary for ground work-- kim ###-#### sean 1 am this moring , he and the general ha d bad communication 5/12/00 4:20:29 PM
Plumbing Rough-in5/10/20005/11/20005/11/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 05/10/2000 at 16:18:56. Contact: ###-####. bakery hand sink 5/11/00 11:26:55 AM
Final5/9/20005/10/20005/10/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 05/09/2000 at 15:38:30. Contact: ###-####. flower shop and bakery, needs ss or brass screws on sinks , caulk sink in floral gz 5/10/00 2:05:31 PM
Groundwork5/8/20005/9/20005/9/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 05/08/2000 at 09:14:53. Contact: ###-####.
Final4/28/20005/1/20005/1/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 04/28/2000 at 15:16:36. Contact: ###-####.
Groundwork4/4/20004/5/20004/5/2000APASS
DetailsLee Rice
Scheduled by a contractor via Hello! on 04/04/2000 at 08:56:39. Contact: ###-####.
Groundwork4/3/20004/3/20004/3/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 04/03/2000 at 08:41:06. Contact: ###-####. gw in foral o


k gz 4/3/00
Plumbing Rough-in3/30/20003/31/20003/31/2000APASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/30/2000 at 13:23:43. Contact: ###-####.
Groundwork3/29/20003/30/20003/30/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/29/2000 at 10:17:42. Contact: ###-####.
Plumbing Rough-in3/29/20003/29/20003/29/2000PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/29/2000 at 07:47:43. Contact: .
Water and/or Sewer3/29/20003/29/20003/29/2000PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/29/2000 at 11:19:08. Contact: ###-####.
Groundwork3/28/20003/28/20003/28/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/28/2000 at 08:43:41. Contact: ###-####.
Plumbing Rough-in3/28/20003/28/20003/28/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/28/2000 at 08:44:06. Contact: ###-####.
Groundwork3/24/20003/24/20003/24/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/24/2000 at 07:49:09. Contact: ###-####.
Groundwork3/22/20003/23/20003/23/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/22/2000 at 08:58:24. Contact: ###-####. early am inspection, 3/23/00 7:51:12 AM
Final3/22/20003/22/20003/22/2000PPART
DetailsGary Ziegler
resrooms in backt 3/22/00 1:48:34 PM
Roof Drains3/22/20003/22/20003/22/2000PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/22/2000 at 08:54:49. Contact: ###-####.
Groundwork3/15/20003/16/20003/16/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/15/2000 at 09:28:02. Contact: ###-####.
Final3/10/20003/13/20003/13/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/10/2000 at 09:45:26. Contact: ###-####.
Groundwork3/9/20003/10/20003/10/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/09/2000 at 11:33:54. Contact: ###-####. am inspect partial grease line/ combo waste by bakery. 3/14/00 11:28:36 AM
Groundwork3/6/20003/6/20003/6/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 03/06/2000 at 08:30:24. Contact: ###-####.
Groundwork2/29/20002/29/20002/29/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 02/29/2000 at 09:30:58. Contact: ###-####. coffee areas part R/I. 3/1/00 11:20:10 AM
Groundwork2/21/20002/22/20002/22/2000APASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 02/21/2000 at 16:22:39. Contact: ###-####.
Groundwork2/16/20002/17/20002/17/2000APART
DetailsLee Rice
FOR COFFEE KEYOSK---###-####-KIM--FOR GROUND WORK G/W coffe keyosk. 2/17/00 2:13:32 PM
Final1/26/20001/27/20001/27/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/26/2000 at 13:27:31. Contact: ###-####. final meat and fish has correction 1/31/00 8:55:55 AM
Groundwork1/20/20001/20/20001/20/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/20/2000 at 10:10:46. Contact: ###-####. Asile 2 GW. 1/21/00 8:52:20 AM
Groundwork1/18/20001/18/20001/18/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/18/2000 at 08:13:54. Contact: .
Plumbing Rough-in1/14/20001/14/20001/14/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/14/2000 at 08:41:27. Contact: ###-####. Meat dept. cover. 1/18/00 8:58:37 AM
Groundwork1/12/20001/13/20001/13/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/12/2000 at 16:28:42. Contact: ###-####. 4:00 am Asile #2 part.
Groundwork1/13/20001/13/20001/13/2000PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/13/2000 at 10:55:22. Contact: ###-####. Fish & meat GW complete. 1/14/00 2:22:54 PM
Groundwork1/12/20001/12/20001/12/2000PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/12/2000 at 08:20:09. Contact: ###-####. Partial GW fish & meat.
Groundwork1/12/20001/12/20001/12/2000APART
DetailsGary Ziegler
Asile #2 case drains "Partial" 3:30 am.
Groundwork1/11/20001/11/20001/11/2000PPART
DetailsGary Ziegler
Meat & fish area.
Groundwork1/10/20001/11/20001/11/2000APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/10/2000 at 08:17:48. Contact: ###-####. Tied back into correct 5" rain drain & tested & certified capped off 4" waste that rain drain was tied into.
Groundwork1/11/20001/11/20001/11/2000PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/11/2000 at 10:23:23. Contact: ###-####. Meat & fish.
Groundwork1/7/20001/7/20001/7/2000AFAIL
DetailsGary Ziegler
5" rain drain- existing tie in new won't drain require camera- results.
Groundwork1/5/20001/5/20001/5/2000PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 01/05/2000 at 09:26:38. Contact: ###-####. 4" waste U.G. N.W. corner.
Other12/29/199912/29/199912/29/1999PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 12/29/1999 at 08:10:52. Contact: ###-####.
Plumbing Rough-in12/28/199912/28/199912/28/1999PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 12/28/1999 at 07:54:11. Contact: ###-####.
Water and/or Sewer12/28/199912/28/199912/28/1999PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 12/28/1999 at 07:54:48. Contact: ###-####.
Groundwork12/23/199912/23/199912/23/1999APASS
DetailsGary Ziegler
Groundwork dairy cooler/exsisted upstair restrooms.
Groundwork12/22/199912/22/199912/22/1999APASS
DetailsGary Ziegler
Groundwork produce.
Groundwork12/21/199912/21/199912/21/1999APASS
DetailsGary Ziegler
Groundwork produce.
Final12/16/199912/16/199912/16/1999PPASS
DetailsGary Ziegler
TEMP FN FOR THE PRODOCE WORK AREA -###-####-JENNIFER
Plumbing Rough-in12/15/199912/15/199912/15/1999PPART
DetailsGary Ziegler
R/I FOR PHARMACY ONLY ###-#### Move from old pharmacy to new remove face and floor of cabinet that inecses.
Final12/14/199912/14/199912/14/1999PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 12/14/1999 at 09:34:29. Contact: ###-####. Veggie sink.
Groundwork12/7/199912/7/199912/7/1999PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 12/07/1999 at 10:16:25. Contact: ###-####.
Groundwork12/3/199912/6/199912/6/1999APART
DetailsGary Ziegler
between 2 and 3 am per Gary ###-####
Plumbing Rough-in12/3/199912/3/199912/3/1999PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 12/03/1999 at 08:29:01. Contact: ###-####.