Final | 2/1/2000 | 2/2/2000 | 2/2/2000 | A | PASS |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 02/01/2000 at 11:40:05. Contact: ###-####.
|
Plumbing Rough-in | 12/13/1999 | 12/14/1999 | 12/14/1999 | A | PASS |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/13/1999 at 16:05:03. Contact: ###-####.
|
Final | 12/10/1999 | 12/13/1999 | 12/13/1999 | A | FAIL |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/10/1999 at 14:15:52. Contact: ###-####.
|
Plumbing Rough-in | 12/9/1999 | 12/10/1999 | 12/10/1999 | A | FAIL |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 14:54:42. Contact: ###-####. Conference
|
Plumbing Rough-in | 12/9/1999 | 12/9/1999 | 12/9/1999 | P | FAIL |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 08:33:44. Contact: ###-####. Not ready.
|
Plumbing Rough-in | 12/8/1999 | 12/8/1999 | 12/8/1999 | P | FAIL |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/08/1999 at 09:48:21. Contact: ###-####.
|