First Notice | 7/22/2015 | 7/22/2015 | 8/11/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed notice
|
BLD-Final | 7/28/2015 | 7/28/2015 | 7/28/2015 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
DOC - Permit Finaled | 7/28/2015 | 7/28/2015 | 7/28/2015 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 7/27/2015 | 7/28/2015 | 7/28/2015 | A | CANC |
Troy Cobbley
|
|
|
Life Safety sign off not required.
|
FIRE-Final Inspection | 7/24/2015 | 7/24/2015 | 7/24/2015 | P | FAIL |
Troy Cobbley
|
|
|
The city approved plans are not complete
|
CHANGE STATUS TO (ISS) | | | 7/24/2015 | | DONE |
|
|
|
Still need a fire life saftey. Spoke with Jim Sly and he gave the ok to reopen the permit to do so.
|
FIRE-Final Inspection | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need city approved plans on site for inspection
|
BLD-Final | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
DOC - Permit Finaled | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | PASS |
Jim Sly
|
|
|
|
BLD-Footing | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | PASS |
Jim Sly
|
|
|
Ken Phone #: ###-####
|
BLD-Footing | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PART |
Jim Sly
|
|
|
Ken Phone #: ###-#### Footings for 4 carports only......OK
|
Issue PAID IN FULL permit | | | 6/4/2015 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 6/4/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 6/1/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 6/1/2015 | | DONE |
|
|
|
Need R.P., Contractor Form, & Certificate of Value
|
Plan assigned to (CDM) | 5/8/2015 | 5/8/2015 | 5/30/2015 | | PASS |
Carl D Madsen
|
|
|
New due 6/8
|
Routing - PLAN CHECK | 5/8/2015 | | 5/30/2015 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 5/30/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/30/2015 | | DONE |
|
|
|
|
Routing - FIRE | 5/8/2015 | | 5/19/2015 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - PLANNING Land Div | 5/8/2015 | | 5/18/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Solid Waste | 5/8/2015 | | 5/13/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing PW Drainage | 5/8/2015 | | 5/11/2015 | | PASS |
Jason C. Taylor
|
|
|
No requirements as project was designed for carports. Jason Taylor ###-####.
|
Routing - Erosion and Sediment | 5/8/2015 | | 5/11/2015 | | PASS |
Evan Jenkins
|
|
|
Install 7 (4 Stall Carport) at Bristlegrove Apartments
|
Routing - Addressing | 5/8/2015 | | 5/8/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2015 | | 5/8/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 5/8/2015 | | 5/8/2015 | | PASS |
Josh Wilson
|
|
|
DRH15-00174
|
Intake Approval | | | 5/8/2015 | | FAIL |
|
|
|
Please provide the completed form 502 checklist with all required items.
|
Intake Approval | | | 5/8/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 5/8/2015 | | 5/8/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 5/6/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2015 4:06PM
|