Print Statement | | | 11/27/2017 | | DONE |
|
|
|
|
First Notice | | 10/13/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
BLD-Final | 10/2/2017 | 10/3/2017 | 10/3/2017 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####. ok for perm occ!!
|
Permanent Occupancy | | | 10/3/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/2/2017 | 10/2/2017 | 10/2/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Dave Phone #: ###-####
|
BLD-Final | 9/19/2017 | 9/20/2017 | 9/20/2017 | A | NR |
Mike Jordan
|
|
|
Eric-please call to meet Phone #: ###-####. Provide the panic hardware as noted on the plans. Life/safety final failed as well.
|
FIRE-Final Inspection | 9/19/2017 | 9/19/2017 | 9/19/2017 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents on site. We accessed the fire review notes on line and I pointed out that it appears panic hardware is required for both exits. Eric Phone #: ###-####-please call to meet
|
Print Occupancy Form | | | 9/19/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/19/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/28/2017 | 7/28/2017 | 9/11/2017 | | DONE |
Julie Romig
|
|
|
08/24 (09/08) - 520 DBMA - Review history and talk to Carl Westfall/Mike Jordan
|
Routing - PLAN CHECK | 7/28/2017 | | 9/11/2017 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 9/11/2017 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/11/2017 | | DONE |
|
|
|
Need
ACHD
GC Form
Revised Cert of Value
|
Plan Reviewer's activity | | | 9/7/2017 | | DONE |
Julie Romig
|
|
|
Spoke with applicant, Eric Holloway and clarified the time frame began 7/28 when fees were paid and that review time frames are 2-3 weeks behind and review will be complete by the week of 9/11. Notify applicant when review is complete.
|
Routing - FIRE | 7/28/2017 | 7/28/2017 | 8/4/2017 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
Intake Approval | | | 7/28/2017 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 7/28/2017 | | 7/28/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 7/28/2017 | | 7/28/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/28/2017 | | 7/28/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan Reviewer's activity | | | 7/26/2017 | | PASS |
|
|
|
Plan intake review approved
|
Application received | | | 7/18/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2017 4:53PM
|