(St. Luke's Children's Pavilion) This permit if for the construction of the Sky Bridge and tenant building out for the 3 story below grade parking garage and 4 story medical office with an occupied roof. Scope of work includes tenant improvement build out, envelope, sky bridge, mechanical, electrical, plumbing and fire systems. This project consist of multiple permits including BLD17-00090 Structural Steel and Concrete, GRD16-00070 Shoring, Grading, Drainage and Site Utilities.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  8/13/2020 DONE
1st past due
Print Statement  7/22/2020 DONE
1st mailed statement
Third Notice 3/14/20204/3/2020 DONE
emailed curtis 4-3-2020
Third Notice 2/12/20203/9/2020 DONE
emailed curtis 3-9-20
Third Notice 12/7/20192/7/2020 DONE
emailed victoria and curtis 2-7-20
Third Notice 11/3/201912/2/2019 DONE
emailed curtis 12-2-19
Third Notice 9/25/201910/29/2019 DONE
emailed curtis 10-29
Second Notice 8/23/20199/20/2019 DONE
emailed curtis 9-20-19
First Notice 8/10/20198/13/2019 DONE
emailed curtis 8-13
BLD-Final7/31/20197/31/20197/31/2019PPASS
DetailsDave Hannah
Justin Phone #: ###-####
FIRE-Final Inspection7/30/20197/31/20197/31/2019APASS
DetailsJim Page
Fire sprinkler inspections are complete, fire alarm inspections are complete, fire extinguishers are placed with current inspection tags. Previously noted items have been corrected that were noted in last fire conference. Final life fire safety inspection complete.

Justin Phone #: ###-####
Permanent Occupancy  7/31/2019 DONE
Zoning Approval7/30/20197/30/20197/30/2019 PASS
DetailsJosh Wilson
PubWorks Occupancy Approval7/30/20197/30/20197/30/2019 DONE
DetailsTiffany Lowery
Street light bond in place. Ok to sign off perm occupancy for PW
BLD-Conference7/19/20197/22/20197/22/2019ADONE
DetailsJim Page
Fire conference complete, fire alarm interface between main site fire alarm system and CP building complete.

fire life safety consult // Justin Phone #: ###-####
BLD-Final6/11/20196/12/20196/12/2019APART
DetailsDave Hannah
Justin Phone #: ###-#### ok for temp occ
FIRE-Final Inspection6/11/20196/11/20196/11/2019APART
DetailsJim Page
Partial final inspection complete for life fire safety. Per conversation with Ron Johnson a 45 day TCO is autorized for life fire safety. Remaining items to inspect before life fire safety can be finaled are: Sigange by the exterior of the building on least one stairwell stating roof top access, finish fire proof wrapping of non essential items for fire pump in fire pump room, closer springs on stairwell gates preventing people from going to the basement in an emergency need to be tensioned or replaced with no exit signage placed on mentioned gates, provide fire alarm notification in sound booth as discussed as well as network the fire alarm control panels together from main site to new building as discussed (network requirement verified with Lee Meridith, fire alarm plan reviewer).
FIRE-Conference6/10/20196/11/20196/11/2019ADONE
DetailsJim Page
Fire conference complete.

Justin Phone #: ###-####
FIRE-Conference5/29/20195/30/20195/30/2019ADONE
DetailsJim Page
Fire conference complete.

Justin Phone #: ###-####
BLD-Other5/21/20195/23/20195/23/2019ACANC
DetailsDave Hannah
Egress // Justin Phone #: ###-####
Print Occupancy Form  5/20/2019 DONE
FIRE-Conference4/8/20194/9/20194/9/2019PCANC
DetailsJim Page
Fire conference will be rescheduled per conversation with the point of contact, this request is cancelled.

Requesting 1st life safety walk; pre-final conference in conjunction with scheduled fire sprinkler final testing being performed by TVFP on same date/time at location. Superintendent - Jamal Nelson Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection3/28/20193/29/20193/29/2019PPASS
DetailsDave Hannah
Inspection of 4th floor shaft wall assemblies and ceiling grid; early afternoon preference; please call Superintendent-Jamal Nelson, 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection3/25/20193/27/20193/28/2019PNR
DetailsDave Hannah
Shaft wall assemblies and ceiling grid on level 4; please call Superintendent 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection3/6/20193/8/20193/8/2019APASS
DetailsDave Hannah
2nd floor in-fill ceiling; 3rd floor shaft wall assemblies and ceiling grid; 4th floor shaft wall assemblies. Please call Superintendent - Jamal Nelson, 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Ceiling Grid Inspection2/18/20192/20/20192/21/2019PPASS
DetailsDave Hannah
Ceiling grid inspection level 1-2; approval to place ceiling tile. Please call Jamal Nelson, 5min prior to arrival - thank you. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Other2/13/20192/14/20192/15/2019PPART
DetailsDave Hannah
Shaft wall assemblies Levels 1-2; approval for ceiling cover. Call Jamal Nelson 5min prior to arrival if possible. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in2/1/20192/4/20192/5/2019PPART
DetailsDave Hannah
Shaft wall assembly - level 2 exhaust; please call Jamal Nelson on arrival Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in1/31/20192/1/20192/1/2019PDEFR
DetailsBrandon Shaw
Shaft wall assembly - level 2 exhaust; please call Jamal Nelson on arrival Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in1/25/20191/25/20191/25/2019PPART
DetailsDave Hannah
Interior framing Level 4; shaft wall assemblies Levels 1-3 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in1/14/20191/17/20191/17/2019PPASS
DetailsDave Hannah
Interior framing 4th floor Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in12/17/201812/18/201812/18/2018APART
DetailsDave Hannah
shaft wall assemblies on levels 2 and 3. Phone #: ###-#### Inspection requested via web by Jamal Nelson ok to cover outter layers two large mec shafts
BLD-Other12/10/201812/12/201812/12/2018ADONE
DetailsDave Hannah
Skybridge placement - review game plan for moving and setting bridge in place. Please call Jamal Nelson 20min prior to arrival. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/27/201811/28/201811/29/2018PDONE
DetailsDave Hannah
Review of mechanical shafts and damper locations Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/15/201811/20/201811/28/2018PCANC
DetailsDave Hannah
Stephen Proctor - Summit Wall: Shaft wall assemblies Level 2; Interior framing on L4; drywall hanging on L3. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/27/201811/27/201811/28/2018PPEND
DetailsDave Hannah
Stephen Proctor - Summit Wall: Shaft wall assemblies Level 2; Interior framing on L4; drywall hanging on L3. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/26/201811/26/201811/27/2018PPEND
DetailsDave Hannah
Stephen Proctor - Summit Wall: Shaft wall assemblies Level 2; Interior framing on L4; drywall hanging on L3. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in11/6/201811/8/201811/9/2018PPASS
DetailsDave Hannah
interior framing level-3 ; 4; exterior framing and shaft walls level-4 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in8/23/20188/24/20188/27/2018PPART
DetailsDave Hannah
Interior wall framing Level-2; Exterior wall framing Level-3 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in8/15/20188/16/20188/17/2018PPASS
DetailsDave Hannah
Framing inspection Level 1 - pre drywall hanging
Jamal Nelson - Superintendent Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Framing/Rough-in6/13/20186/14/20186/14/2018PPEND
DetailsDave Hannah
Interior framing and spray applied fire proofing in progress on 1st-2nd floor; would like to walk building with Inspector and familiarize with project. Phone #: ###-#### Inspection requested via web by Jamal Nelson
Issue PAID IN FULL permit  4/10/2018 DONE
Permit Ready to Issue  4/5/2018 DONE
Need:
ACHD-MET
GC form
Cert of value from GC
Plan assigned to (AJS)8/16/20178/16/20174/4/2018 PASS
DetailsAdele J Schaffeld-Griffin
1st reveiew completed St Lukes Pavillion
Routing - PLAN CHECK4/4/2018 4/4/2018 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  4/4/2018 DONE
Routing - PLAN CHECK2/22/2018 3/31/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL2/22/2018 2/26/2018 PASS
DetailsAdele J Schaffeld-Griffin
Extend Review Timeline  1/24/2018 DONE
1st Approved 180 day extension per Adele. See documents
Routing - PLAN CHECK10/27/2017 11/21/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL10/27/2017 11/21/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Route to Impact Fee Review10/6/201710/9/201711/7/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLUMBING10/27/2017 11/1/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing PW Flood Plain10/27/2017 10/31/2017 PASS
DetailsJason C. Taylor
Flood wall on Ave B is shown on plans. Wall to be approximately 2' above first floor elevation. Jason Taylor ###-####
Routing PW Street Lights10/27/2017 10/27/2017 PASS
DetailsTom Marshall
1st review completed  10/6/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK8/16/2017 10/6/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Environmental8/18/2017 9/25/2017 PASS
DetailsRick Christenson
Routing PW Street Lights8/18/2017 9/15/2017 FAIL
DetailsTom Marshall
Need street lights at both driveways.
Routing PW Flood Plain8/21/2017 9/6/2017 FAIL
DetailsJason C. Taylor
See changemark in ePlan. JCT
Routing Off Site - STRUCTURAL8/16/2017 8/30/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE8/16/20178/16/20178/28/2017 PASS
DetailsScott Arellano
Attached comments to plans.
Routing - Design Review8/16/2017 8/28/2017 PASS
DetailsSarah Schafer
Routing PW Geothermal8/18/2017 8/24/2017 PASS
DetailsJon R. Gunnerson
No commitment to connect onto geothermal. If this building desires to connect onto Boise Geothermal System, contact Public Works @ ###-####
Routing - PLUMBING8/16/2017 8/23/2017 FAIL
DetailsBill VanDegrift
resubmit showing 4" pumped waste referenced in note 3 page P101 connecting to appropriately sized waste.

general redlines that do not need to be addressed
1) double combos are not allowed in the horizontal position.
2) install a double check valve at the coffee maker for standard coffee makers. P401
3) a PVB will be required at the eyewash if the hose can be submerged in the mop sink. P401
4) piping to floor drainage in fire pump and water rooms must be 4". P102
5) pipe condensate from control room in garage to area drain. page P101 and P102
6) there is no design for a med gas and vacuum system, if one is to be installed additional plans will need to be submitted

Routing - PUBLIC WORKS8/16/2017 8/23/2017 PASS
DetailsRachael Beierle
Routing PW Sewer Design8/18/2017 8/23/2017 PASS
DetailsKyle S. Rosenmeyer
Utility connections previously approved under foundation or grading permit (can't remember which). No civil sheets included in this submittal.
Routing - PLANNING8/16/2017 8/22/2017 PASS
DetailsDavid Moser
Routing - MECHANICAL8/16/2017 8/22/2017 PASS
DetailsTroy James
Routing PW Drainage8/18/2017 8/22/2017 PASS
DetailsBrian Murphy
Routing PW Solid Waste8/18/2017 8/21/2017 PASS
DetailsEvan Carpenter
Routing - Erosion and Sediment8/16/2017 8/18/2017 PASS
DetailsAndy J. Long
already covered under ESC16-01167
Routing - Addressing8/16/2017 8/17/2017 PASS
DetailsDoug Chausow
Intake Approval  8/16/2017 PASS
DetailsAdele J Schaffeld-Griffin
Intake Approval  8/14/2017 FAIL
DetailsAdele J Schaffeld-Griffin
see mark ups on checklist
Application received  8/7/2017 DONE
Application submitted via PDS Online on Aug 7 2017 10:44AM