Permit Information
Permit NumberBLD17-03344
StatusFinaled
Name ANDERSEN CONSTRUCTION COMPANY IDAHO
Site Address 880 W RIVER ST
Project NameThe Afton Phase II - Podium
Customer NumberGRD17-00061
ePlanReviewYes
Description
(THE AFTON – CONCRETE PARKING GARAGE PODIUM OF PHASE II – WEST BUILDING) (DRH17-00213) The fire sprinkler system (NFPA 13 below and above the podium) is used for story, height, and building area increase. The apartment building will be constructed on top of the podium under permit BLD17-03345. To construct the concrete parking garage podium portion of Phase II (West building) of the Afton development. All other drawings are for reference only. When the entire building is completed, uses are expected to include parking, storage, and perhaps office, retail sales, or assembly on the 1st story; two story residential condominiums on the 2nd story; and 1 story residential condominiums on the 2nd, 3rd, 4th, and 5th stories. Work under this permit includes concrete continuous footings, concrete spread footings, concrete matt footings, concrete foundations, 3-hr concrete shear walls and bearing walls, 3-hr concrete columns, 3-hr two-way post tensioned concrete podium, and a concrete slab on grade. The podium (i.e. floor of 2nd story) will be a 12 inch thick post tensioned concrete slab having a 3-hr fire-resistance-rating. Penetrations for plumbing pipes, roof drains, hold downs for shear walls, etc. are required to be made without cutting any reinforcement, including post tensioned tendons. Special Inspection is required for soils, concrete including post tensioning, masonry, steel including welding, anchors post-installed in hardened concrete, fire-resistance-rated through penetration fire stops, etc. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The permit for the entire building shall not be finaled and a Certificate of Occupancy shall not be issued until the condo plat that removes the interior property line is completed. This permit does not establish a Certificate of Occupancy for any portion of this building. Fire sprinkler permits and fire alarm permits are required in conjunction with future building permits. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  12/12/2019 DONE
Doc final per inspection conducted on 12/09/2019 by David Hannah and confirm with him
BLD-Final12/6/201912/9/201912/9/2019APASS
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Framing/Rough-in12/6/201912/9/201912/9/2019ADONE
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Final12/6/201912/9/201912/9/2019APASS
DetailsDave Hannah
BLD-Framing/Rough-in12/6/201912/6/201912/6/2019PCANC
DetailsJim Storey
Jason Phone #: ###-#### no access or call back.
BLD-Framing/Rough-in12/5/201912/6/201912/6/2019ADEFR
DetailsBrandon Shaw
Jason Phone #: ###-####
FIRE-Final Inspection12/5/201912/6/201912/6/2019APASS
DetailsJim Page
Final life fire safety inspection is complete.

Jason Phone #: ###-####
FIRE-Final Inspection9/24/20199/24/20199/24/2019APART
DetailsJim Page
Partial final inspwection for life fire safety is complete, item left for life fire safety is signage placed in north stairwell, install signage for fire sprinkler floor control access at discussed doors. Fire sprinkler inspection is complete, fire alarm inspection is complete. 45 day TCO authorized per conversation with Ron Johnson for life fire safety.
PubWorks Occupancy Approval9/23/20199/23/20199/23/2019 DONE
DetailsTiffany Lowery
Zoning Approval9/17/20199/17/20199/17/2019 PASS
DetailsKatelyn Menuge
BLD-Framing/Rough-in5/16/20195/16/20195/16/2019APART
DetailsDave Hannah
5th floor drop soffit framing Phone #: ###-#### Inspection requested via web by Jason Reisinger first four rooms ok
BLD-Framing/Rough-in5/13/20195/14/20195/14/2019APART
DetailsDave Hannah
Jason Phone #: ###-#### 2nd floor corradors drop ceilings ok to cover
BLD-Framing/Rough-in9/27/20189/27/20189/27/2018PPEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Framing/Rough-in8/24/20188/24/20188/27/2018PNR
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Foundation7/18/20187/18/20187/18/2018PPASS
DetailsDave Hannah
post tension // Jason Phone #: ###-####
BLD-Footing4/24/20184/24/20184/25/2018PPEND
DetailsDave Hannah
Jason Phone #: ###-#### crews still working on forms and rebar also spec inspection will do final rebar and test concrete
Print permit w/o conditions  4/18/2018  
Issue PAID IN FULL permit  2/20/2018 DONE
Inspection Record Card- Bld  2/20/2018 DONE
OVERRIDE  1/18/2018  
Route to Impact Fee Review1/12/20181/15/20181/18/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan assigned to (CJW)12/1/201712/1/20171/18/2018 PASS
DetailsCarl Westfall
(2nd done) (Dec 14 - 2 weeks) (66 sheets) Afton Podium
Routing - PLAN CHECK1/17/2018 1/18/2018 PASS
DetailsCarl Westfall
2nd review done
Routing Off Site - STRUCTURAL1/18/2018 1/18/2018 DONE
DetailsCarl Westfall
For Jared Bauder with CH2M Hill to remove his changemarks
Routing PW Solid Waste1/18/2018 1/18/2018 PASS
DetailsEvan Carpenter
For Evan to remove his changemark.

ESC: Changemark resolved.
PLANS/APPL TAKEN TO FRONT DESK  1/18/2018 DONE
Permit Ready to Issue  1/18/2018 DONE
DetailsChristina Prado
NEED
ACHD
RP - met
GC FORM - met
REVISED CERT - met
(BREAK OUT VALUES FOR GRD17-00061 AND ISSUE BOTH PERMITS)
Plan resubmittals received  1/17/2018 DONE
Routing - PLAN CHECK12/20/2017 1/12/2018 FAIL
DetailsCarl Westfall
1st review completed  1/12/2018 DONE
Plan resubmittals requested  1/12/2018 DONE
Routing Off Site - STRUCTURAL12/21/2017 1/2/2018 PASS
DetailsCarl Westfall
Jared Bauder (CH2M Hill)
Routing PW Solid Waste12/21/2017 12/29/2017 PASS
DetailsEvan Carpenter
Routing - Design Review12/21/2017 12/26/2017 PASS
DetailsAndrea Tuning
Plan resubmittals received  12/20/2017 DONE
Plan resubmittals requested  12/20/2017 DONE
Routing - PLAN CHECK12/1/2017 12/20/2017 PEND
DetailsCarl Westfall
This project has not been reviewed yet for nonstructural IBC provisions. It was routed back to the applicant so that revised drawings could be uploaded so the 2nd structural review could be done. The IBC non-structural review will be done as as part of the 2nd review.
Routing Off Site - STRUCTURAL12/1/2017 12/12/2017 FAIL
Jared Bauder (CH2M Hill)
Routing PW Solid Waste12/5/2017 12/11/2017 FAIL
DetailsEvan Carpenter
There will need to be a loading zone on 9th street where the dumpsters can be placed prior to servicing by the City’s contractor. Refer to the solid waste design standards linked below, particularly to the requirement to “provide a ‘no parking area’ on the street, for a minimum of 10’ in front of the access ramp.”

Additionally, I will need a signed statement from the building owner, stating that building staff will be responsible for moving containers to the street loading zone for collection and that the City’s solid waste contractor will not enter the building to retrieve or return the containers from the solid waste room.
Routing - FIRE12/1/201712/1/201712/8/2017 PASS
DetailsScott Arellano
Attached comments to plans.
Routing PW Sewer Design12/5/2017 12/8/2017 PASS
DetailsMike Sheppard
Routing PW Sewer Rating12/5/2017 12/6/2017 PASS
DetailsMorgan Webb
FIRST FLOOR PLUMBING ONLY
Routing - Erosion and Sediment12/1/2017 12/6/2017 PASS
DetailsMichael Zawacki
VOID. SWPPP/ESC plan submitted with GRD17-00061. See ESC17-01346 to cover all phases of Afton Phase II.
Routing - PUBLIC WORKS12/1/2017 12/5/2017 PASS
DetailsRachael Beierle
ROUTING ONLY.
Routing PW Drainage12/5/2017 12/5/2017 PASS
DetailsBrian Murphy
Routing PW Street Lights12/5/2017 12/5/2017 PASS
DetailsTom Marshall
Routing PW Environmental12/5/2017 12/5/2017 PASS
DetailsRick Christenson
Trash area drains FD-3, FS-2 routed to FL-1 Interceptor.
Routing PW Geothermal12/5/2017 12/5/2017 PASS
DetailsJon R. Gunnerson
No connection to geothermal heating district. If desiring to connect onto geothermal system, contact Boise Public Works ###-####
Routing - PLANNING12/1/2017 12/4/2017 PASS
DetailsCody Riddle
DR only.
Routing - Design Review12/1/2017 12/4/2017 FAIL
DetailsAndrea Tuning
I just received a building permit package (BLD17-03344) to review. It appears as though the building permit package includes a significantly different site plan, floor plans and elevations than what were approved by the Design Review Committee on July 12, 2017 with DRH17-00213. As such, I am unable to approve your building permit package at this time.

A staff level Design Review application must be reviewed and approved prior to my next review of the building permit package.

Routing - Addressing12/1/2017 12/1/2017 PASS
DetailsDoug Chausow
Intake Approval  12/1/2017 PASS
Plan Reviewer's activity  11/20/2017 PASS
Plan intake review approved
Intake Approval  10/2/2017 FAIL
(10-2-17) Please see the circled items in the plan intake checklist (i.e. the ones without an OK). Please resolve each item as directed.
Intake Approval  9/21/2017 FAIL
(9-21-17) Please see the circled items in the plan intake checklist. Please resolve each item as directed.
Application received  9/19/2017 DONE
Application submitted via PDS Online on Sep 19 2017 9:07AM