BLD-Aging Inspection | 2/19/2020 | 2/19/2020 | 2/19/2020 | | PASS |
Dave Hannah
|
|
|
|
BLD-Concrete | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Dave Hannah
|
|
|
rebar // Ken Phone #: ###-####
|
BLD-Foundation | 10/7/2019 | 10/7/2019 | 10/8/2019 | P | PEND |
Dave Hannah
|
|
|
rebar // Ken Phone #: ###-####
|
BLD-Concrete | 8/16/2019 | 8/19/2019 | 8/27/2019 | A | PASS |
Dave Hannah
|
|
|
Ken- Rebar inspection Phone #: ###-####
|
BLD-Concrete | 8/8/2019 | 8/8/2019 | 8/8/2019 | P | DONE |
Dave Hannah
|
|
|
ken Phone #: ###-####
|
BLD-Foundation | 7/16/2019 | 7/16/2019 | 7/18/2019 | P | PASS |
Dave Hannah
|
|
|
Ken Phone #: ###-####
|
BLD-Footing | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Mike Jordan
|
|
|
slab on deck // Ken Phone #: ###-####
|
BLD-Foundation | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PEND |
Dave Hannah
|
|
|
Ken-slab on deck Phone #: ###-#### ok after spec inspection
|
BLD-Foundation | 4/23/2019 | 4/24/2019 | 4/25/2019 | P | PART |
Dave Hannah
|
|
|
Ken-concrete rebar Phone #: ###-#### second pour of second floor ok
|
BLD-Concrete | 4/17/2019 | 4/18/2019 | 4/19/2019 | A | PART |
Brandon Shaw
|
|
|
structural slab on deck... Special Instion was on site at time of pour, pending report...
|
BLD-Foundation | 1/23/2019 | 1/23/2019 | 1/23/2019 | P | PEND |
Brandon Shaw
|
|
|
rebar- ok after spec inspection sign offs...
|
BLD-Foundation | 12/19/2018 | 12/20/2018 | 12/20/2018 | P | PEND |
Dave Hannah
|
|
|
Ken Phone #: ###-#### ok after spec inspection sign offs
|
BLD-Foundation | 12/6/2018 | 12/6/2018 | 12/6/2018 | P | PART |
Dave Hannah
|
|
|
rebar- Ken Phone #: ###-#### ok after al oks
|
BLD-Concrete | 12/3/2018 | 12/3/2018 | 12/5/2018 | P | PASS |
Dave Hannah
|
|
|
Ken Phone #: ###-####
|
BLD-Concrete | 12/4/2018 | 12/4/2018 | 12/4/2018 | A | PASS |
Dave Hannah
|
|
|
Ken Phone #: ###-####
|
BLD-Foundation | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | PEND |
Dave Hannah
|
|
|
Ken-foundation reinforcing Phone #: ###-#### ok after spec inspection
|
BLD-Foundation | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Dave Hannah
|
|
|
rebar // Justin Phone #: ###-#### meet with al and walked project
|
Extend Permit 90/180 days | 11/20/2018 | 11/20/2018 | 11/20/2018 | P | CANC |
Dave Hannah
|
|
|
rebar // Justin Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/12/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/12/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 12/1/2017 | 12/1/2017 | 9/10/2018 | | PASS |
Carl Westfall
|
|
|
(3rd done) 12/14/17 (new - 14 days) (ePlan - 108 sheets then increased to 153 sheets) St. Lukes Orthopedic
|
Routing - PLUMBING | 9/4/2018 | | 9/10/2018 | | PASS |
Dan Ediger
|
|
|
See red line corrections
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/10/2018 | | DONE |
|
|
|
MET
|
Routing - PUBLIC WORKS | 9/4/2018 | | 9/4/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 9/4/2018 | | 9/4/2018 | | PASS |
Cody Riddle
|
|
|
|
Routing - Design Review | 9/4/2018 | | 9/4/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 8/31/2018 | | 9/4/2018 | | PASS |
Carl Westfall
|
|
|
|
Routing PW Drainage | 9/4/2018 | | 9/4/2018 | | PASS |
Brian Murphy
|
|
|
Brian needs to add his approval stamp to the most recent drawing
|
Plan resubmittals received | | | 8/31/2018 | | DONE |
|
|
|
|
Routing PW Sewer Design | 3/24/2018 | | 4/3/2018 | | PASS |
Mike Sheppard
|
|
|
|
Plan resubmittals requested | | | 4/3/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/24/2018 | | 4/2/2018 | | PASS |
Carl Westfall
|
|
|
Jared Bauder (CH2MHill)
|
Routing - FIRE | 3/24/2018 | 3/30/2018 | 3/29/2018 | | PASS |
Scott Arellano
|
|
|
3/30 St. Lukes Ortho Structural Resubmittal Eplan
|
Routing - PLANNING | 3/24/2018 | | 3/28/2018 | | FAIL |
Cody Riddle
|
|
|
The record of survey has not been completed and the required easement provided (site specific conditions 2 and 3 from CUP approval).
|
Routing PW Solid Waste | 3/24/2018 | | 3/27/2018 | | PASS |
Evan Carpenter
|
|
|
The solid waste enclosure location is approved as shown.
|
Routing - Design Review | 3/24/2018 | | 3/26/2018 | | FAIL |
Andrea Tuning
|
|
|
Prior to issuance of building permits, a record of survey for a parcel consolidation shall be completed to demonstrate compliance with building code requirements for any construction over or adjacent to property lines.
Stripe the parking stall adjacent to 27th Street to be 20-feet in depth or identify these spaces as compact spaces.
Reduce the proposed screen wall located around the loading area to meet the 10-foot building setback.
Install a minimum of 41 accessible parking stalls on the site.
Provide a minimum of 47 bicycle parking spaces with a minimum of 24 of the bicycle spaces being covered.
for the parking structure.
Obtain a license agreement for landscaping located within the public right-of-way.
Construct the screen wall adjacent to the loading area as a 4-foot tall CMU base with the metal railing extending between the 6-foot columns the additional 2-feet.
Provide additional transparency within the fencing along Fairview Avenue.
Locate all pole lights to be outside of the required setbacks and outside of any required landscape planters.
|
Routing PW Drainage | 3/24/2018 | | 3/26/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 3/23/2018 | | 3/24/2018 | | PASS |
Carl Westfall
|
|
|
Pass pending structural
|
Plan resubmittals received | | | 3/23/2018 | | DONE |
Carl Westfall
|
|
|
|
Route to Impact Fee Review | 1/13/2018 | 1/16/2018 | 1/16/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/13/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/13/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/1/2017 | | 1/13/2018 | | PASS |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 12/1/2017 | | 12/18/2017 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (CH2M Hill)
|
Routing - FIRE | 12/1/2017 | 12/1/2017 | 12/8/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed report to architect. Attached report to case.
|
Routing PW Drainage | 12/8/2017 | | 12/8/2017 | | FAIL |
|
|
|
HOLD PERMIT
|
Routing PW Sewer Design | 12/1/2017 | | 12/8/2017 | | FAIL |
Mike Sheppard
|
|
|
Coordinate with Boise City Public Works for sewer service.
|
Routing PW Solid Waste | 12/1/2017 | | 12/8/2017 | | FAIL |
Evan Carpenter
|
|
|
The solid waste enclosure gates must have at least 12 feet of unobstructed clearance between gate posts for each enclosure. Current bollard placement restricts this clearance to less than 10 feet for each enclosure gate.
|
Routing - Erosion and Sediment | 12/1/2017 | | 12/8/2017 | | PASS |
Michael Zawacki
|
|
|
Dewatering stated in SWPPP. Plan will need to be reviewed and approved before any dewatering activity begins.
|
Routing PW Drainage | 12/1/2017 | | 12/6/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 12/1/2017 | | 12/5/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Street Lights | 12/1/2017 | | 12/4/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - Addressing | 12/1/2017 | | 12/1/2017 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 12/1/2017 | | PASS |
|
|
|
|
Routing - PLANNING | 12/1/2017 | | 12/1/2017 | | FAIL |
Cody Riddle
|
|
|
Site specific conditions 2 and 3 require an access easement and record of survey be complete prior to issuance. Emailed applicant requesting additional information.
|
Routing - PUBLIC WORKS | 12/1/2017 | | 12/1/2017 | | PASS |
Rachael Beierle
|
|
|
STEEL AND CONCRETE PHASE ONLY. NO IMPACT FEES ASSESSED UNTIL TI PHASE.
|
Routing - Design Review | 12/1/2017 | | 12/1/2017 | | FAIL |
Andrea Tuning
|
|
|
Prior to issuance of building permits, a record of survey for a parcel consolidation shall be completed to demonstrate compliance with building code requirements for any construction over or adjacent to property lines.
Stripe the parking stall adjacent to 27th Street to be 20-feet in depth or identify these spaces as compact spaces.
Reduce the proposed screen wall located around the loading area to meet the 10-foot building setback.
Install a minimum of 41 accessible parking stalls on the site.
Provide a minimum of 47 bicycle parking spaces with a minimum of 24 of the bicycle spaces being covered.
for the parking structure.
Obtain a license agreement for landscaping located within the public right-of-way.
Construct the screen wall adjacent to the loading area as a 4-foot tall CMU base with the metal railing extending between the 6-foot columns the additional 2-feet.
Provide additional transparency within the fencing along Fairview Avenue.
Locate all pole lights to be outside of the required setbacks and outside of any required landscape planters.
|
Intake Approval | | | 11/24/2017 | | FAIL |
|
|
|
Please provide the owners signature on form 310.
|
Application received | | | 11/21/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 21 2017 5:06PM
|