Permit Information
Permit NumberBLD17-04467
StatusFinaled
Name RRC CONTRACTORS
Site Address 720 N ALLUMBAUGH ST
Project NameInjury Care EMS
Customer Number 
ePlanReviewYes
Description
(INJURY CARE EMS) **This building is not fire sprinklered. Permit for the remodel of an existing 12,060 sq ft office and warehouse used as a 24-hour ambulance dispatch center and includes garaged parking for vehicles, interior offices, staff lounge, small kitchen, and conference area. A 1,026 sq ft portion of the existing building will be demolished for a total building area of 11,034 sq ft and a portion of the existing storage area will be converted to office. The proposed occupancy classification is B & S-1 and is not approved for “R” occupancy. New interior finishes in compliance with Ch. 8 of the 2012 IBC. All work to be done per the approved plans and applicable codes and ordinances. **JAR**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/16/20194/12/2019 DONE
This permit finaled on the web by derek cooper
Third Notice 3/12/20194/11/2019 DONE
mailed 4-12-19 with firt follow up letter
First Follow up  4/11/2019 DONE
Third Notice 2/11/20193/7/2019 DONE
mailed 3-11
Third Notice 1/13/20192/6/2019 DONE
mailed 2-11-19
Second Notice 12/23/20181/8/2019 DONE
mailed 1-11-19
First Notice 11/10/201812/13/2018 DONE
mailed 12-14
BLD-Final10/31/201810/31/201810/31/2018PPASS
DetailsMike Jordan
Brian Phone #: ###-####. All issues have been resolved. ok for perm occ.
Permanent Occupancy  10/31/2018 DONE
BLD-Final10/30/201810/30/201810/30/2018PNR
DetailsMike Jordan
Brain Phone #: ###-####. Needs to complete handrail extensions
FIRE-Final Inspection10/26/201810/29/201810/29/2018PPASS
DetailsTroy Cobbley
life safety passed

Brain Phone #: ###-####
FIRE-Final Inspection10/24/201810/25/201810/25/2018AFAIL
DetailsTroy Cobbley
Provide immediate shutdown for the hvac unit and correct the sample tube orientation, provide sticker at the main exit and indicator as discussed

Brian Phone #: ###-####
Zoning Approval10/25/201810/25/201810/25/2018 DONE
DetailsAndrea Tuning
BLD-Final7/5/20187/6/20187/6/2018PPART
DetailsJim Sly
Brian Phone #: ###-####
Remodeled area appears to be OK. See previous Fire inspector notes. All trades appear to be completed in remodeled area.
FIRE-Final Inspection7/5/20187/6/20187/6/2018APART
DetailsTroy Cobbley
The remodeled area life safety is passed. Before a final the exit lights/emergency lights/exit discharge lights for the north side bay and the south side bay garage door needs to be installed and tested, also the main exit will need its discharge light, sticker, and indicator.

Brian Phone #: ###-####
BLD-Ceiling Grid Inspection6/18/20186/18/20186/18/2018PPASS
DetailsMike Jordan
Brain Phone #: ###-####
BLD-Energy code compliance5/8/20185/8/20185/8/2018PPASS
DetailsMike Jordan
Brian Phone #: ###-####
BLD-Framing/Rough-in5/8/20185/8/20185/8/2018PPASS
DetailsMike Jordan
Brian Phone #: ###-####. Hardlids ok. fireblocking ok.
BLD-Wall cover4/17/20184/18/20184/18/2018APASS
DetailsMike Jordan
Brian Phone #: ###-####. Interior steel stud framed walls ok. Need to fireblock at fur out walls and encapsulate old foam insulation at old wlak in coolers with non combustible.
Issue PAID IN FULL permit  2/22/2018 DONE
Print Occupancy Form  2/22/2018 DONE
OVERRIDE  2/21/2018  
Plan assigned to (JAR)12/15/201712/15/20172/21/2018 DONE
DetailsJulie Romig
**1st Rev Comp - 3rd Rec'd 2/21 - L3 Remodel for EMS
Routing - Design Review2/21/2018 2/21/2018 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK2/21/2018 2/21/2018 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  2/21/2018 DONE
Permit Ready to Issue  2/21/2018 DONE
Need
GC Form
Revised Cert of Value
RP
Routing - PLAN CHECK2/9/2018 2/20/2018 PASS
DetailsJulie Romig
Routing - Design Review2/20/2018 2/20/2018 FAIL
DetailsAndrea Tuning
ADA spaces shall be 8-feet by 20-feet.
Routing Off Site - STRUCTURAL2/9/2018 2/13/2018 PASS
DetailsJulie Romig
2nd Review - Passed per ePlanReview
Route to Impact Fee Review1/19/20181/22/20181/22/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK12/15/2017 1/19/2018 FAIL
DetailsJulie Romig
Corrections required; see Plan Review Report.
1st review completed  1/19/2018 FAIL
DetailsJulie Romig
Routing Off Site - STRUCTURAL12/15/2017 12/28/2017 FAIL
DetailsJulie Romig
Corrections required per ePlanReview
Routing - FIRE12/15/201712/15/201712/22/2017 PASS
DetailsErika Akin
Attached comments to case
Routing - MECHANICAL12/15/2017 12/19/2017 PASS
DetailsTroy James
Routing - PLUMBING12/15/2017 12/18/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing - Addressing12/15/2017 12/15/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/15/2017 12/15/2017 PASS
DetailsMorgan Webb
WEST BOISE SEWER DISTRICT
Routing - Erosion and Sediment12/15/2017 12/15/2017 PASS
DetailsAndy J. Long
ESC plan with narrative and site map approved by certified PD. RP TBD, site preparation inspection required.
Routing - Design Review12/15/2017 12/15/2017 FAIL
DetailsAndrea Tuning
Install terminal planters at the end of each row of parking to be a minimum of 8-feet in width (measured inside of curb to inside of curb). Provide the required Class II tree and groundcover within each of the terminal planters. This will require the planter located next to the three new spaces to be widened.
Intake Approval  12/15/2017 PASS
DetailsAdele J Schaffeld-Griffin
Michael accepted pre screen. Adele notified Architect Jerrod that this will route as Major TI.
Application received  12/7/2017 DONE
Application submitted via PDS Online on Dec 7 2017 3:37PM
Routing - Design Review2/9/2018   FAIL
DetailsAndrea Tuning
Install terminal planters at the end of each row of parking to be a minimum of 8-feet in width (measured inside of curb to inside of curb). Provide the required Class II tree and groundcover within each of the terminal planters. This will require the planter located next to the three new spaces to be widened.

ADA spaces shall also be 20-feet deep or 18-feet with a 2-foot bumper overhang. If there is a bumper overhang, the adjacent sidewalk is requried to be 6-feet in width.

All pedestrian sidewalks must be 5-feet in width.