PubWorks Occupancy Approval | 10/16/2019 | 10/16/2019 | 10/16/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 10/15/2019 | | DONE |
|
|
|
|
Zoning Approval | 10/14/2019 | 10/14/2019 | 10/14/2019 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Final | 9/26/2019 | 9/27/2019 | 9/27/2019 | P | PASS |
Brandon Shaw
|
|
|
call rob 2089990578 Phone #: ###-#### Inspection requested via web by J.C. Murray
|
DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 9/26/2019 | 9/27/2019 | 9/27/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, heat trace inspection has been completed, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete, signatures have been provided on final sign off card for associated trades.
call rob 2089990578 Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Ceiling Grid Inspection | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | PART |
Jim Storey
|
|
|
Bld K , west side tower. drop ceilings for cover. Fire Caulking Phone #: ###-#### Inspection requested via web by J.C. Murray 3 spk oversized face layer gyp holes to fire stop/ ele 1 st floor over seized hole
|
BLD-Energy code compliance | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | PASS |
Brandon Shaw
|
|
|
bld K - west side energy code compliance, insulation. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Energy code compliance | 5/15/2019 | 5/16/2019 | 5/16/2019 | A | PASS |
Jim Storey
|
|
|
Bld K - east side insulation. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 5/8/2019 | 5/9/2019 | 5/9/2019 | A | PASS |
Jim Storey
|
|
|
Bld K - fire caulking Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PASS |
Jim Storey
|
|
|
Bld K; framing inspection; anchor bolts, hold downs, straps, exterior nailing and truss engineering. Phone #: ###-#### Inspection requested via web by J.C. Murray 480 c/n pass.
|
BLD-Wall Bracing | 3/12/2019 | 3/12/2019 | 3/13/2019 | P | CANC |
Brandon Shaw
|
|
|
First floor hold downs; exterior sheathing and shear walls and straps, good to go... Third floor, Rm 303, need truss Engineering fix or approval for A5A installed in wrong location...
|
BLD-Wall Bracing | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PART |
Jim Sly
|
|
|
Craig Phone #: ###-#### 25 lin. ft of 2 walls..East end of Bldg. K 1st floor.
|
BLD-Foundation | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | PASS |
Jim Storey
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Brandon Shaw
|
|
|
Manuel Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/10/2018 | | DONE |
|
|
|
plan mod
|
OVERRIDE | | | 7/3/2018 | | |
|
|
|
|
Plan assigned to (AJS) | 6/26/2018 | 6/26/2018 | 7/3/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 7/2/2018 | | 7/3/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 7/2/2018 | | 7/3/2018 | | CANC |
Adele J Schaffeld-Griffin
|
|
|
|
Permit Ready to Issue | | | 7/3/2018 | | DONE |
|
|
|
PLAN MOD (17-04623, 04624, 4625, 4627, 4628, 4630, 4631)
|
Routing - PLAN CHECK | 7/2/2018 | | 7/2/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
PLAN MOD RELOCATE WAHER/DRYER FROM BATHROOM TO HALLWAY ADD CLOSED DOOR AS NOTED ON APPROVED PLANS 7-2-18**AJS**
|
Plan Modification Accepted | | | 6/26/2018 | | DONE |
|
|
|
started workflow for modification; Type 2 - Relocate the wsher/dryer from the bathroom to the hallway. Add pocket door to bedroom closet. Type 2-HC - Add pocket door to bedroom closet. Type 5 - Relocate the washer dryer from the bathroom to the hallway and reconfigure bathroom. Type 5-HC - Remove closet adjacent to kitchen counter.
|
Print Occupancy Form | | | 5/16/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/16/2018 | | DONE |
|
|
|
|
Expiration Notice | 5/15/2018 | 6/5/2018 | 5/15/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 5/2/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 5/2/2018 | | DONE |
Christina Prado
|
|
|
all met
|
Plan assigned to (AJS) | 1/9/2018 | 1/9/2018 | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Skyline Apartments
|
Routing - PLUMBING | 1/9/2018 | | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
SIGNED OFF IN E PLAN
|
Routing - PLAN CHECK | 5/1/2018 | | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing Off Site - STRUCTURAL | 5/1/2018 | | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Design Review | 4/2/2018 | | 4/2/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 2/12/2018 | 2/15/2018 | 2/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/12/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 1/9/2018 | | 2/12/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing Off Site - STRUCTURAL | 1/9/2018 | | 2/12/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Sewer Design | 1/9/2018 | | 1/25/2018 | | PASS |
Mike Sheppard
|
|
|
approval per ePlan
|
Routing - Erosion and Sediment | 1/9/2018 | | 1/23/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Petra needs to designate their own RP. Site preparation inspection required. See also ESC17-01754
|
Routing - FIRE | 1/9/2018 | 1/9/2018 | 1/10/2018 | | PASS |
Scott Arellano
|
|
|
See Fire Code plan review comments previously approved under BLD15-03963.
|
Routing - MECHANICAL | 1/9/2018 | | 1/10/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Sewer Rating | 1/9/2018 | | 1/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 1/9/2018 | | 1/10/2018 | | PASS |
Nicolette Womack
|
|
|
Required to provide 192 bicycle spaces.
|
Routing - Addressing | 1/9/2018 | | 1/9/2018 | | PASS |
Doug Chausow
|
|
|
Address: 2087 S Hudson Ave
|
Routing - PUBLIC WORKS | 1/9/2018 | | 1/9/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 1/9/2018 | | 1/9/2018 | | FAIL |
Katelyn Menuge
|
|
|
Corrections to landscape and light pole locations required.
|
Intake Approval | | | 1/9/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Solid Waste | 1/9/2018 | | 1/9/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 1/9/2018 | | 1/9/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 1/9/2018 | | 1/9/2018 | | PASS |
Tom Marshall
|
|
|
|
Application received | | | 12/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 22 2017 11:30AM
|
First Notice | | 10/25/2019 | | | |
|
|
|
|
First Notice | 9/27/2019 | 9/27/2019 | | | |
Brandon Shaw
|
|
|
|