BLD-Final | 2/13/2019 | 2/13/2019 | 2/14/2019 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
DOC - Permit Finaled | 2/14/2019 | 2/14/2019 | 2/14/2019 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | PASS |
Dave Hannah
|
|
|
Fire place was installed, inspected and approved. I need approval to dry wall fire place. Phone #: ###-#### Inspection requested via web by Chris Eby
|
BLD-Energy code compliance | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-#### everything but fireplace ok to rock
|
BLD-Framing/Rough-in | 11/7/2018 | 11/7/2018 | 11/8/2018 | P | PART |
Dave Hannah
|
|
|
Please call 30 minutes prior to inspection. Phone #: ###-#### Inspection requested via web by Chris Eby ok to insulate needs to fire block mec chasses and add piont loads studs under beams
|
BLD-Energy code compliance | 11/7/2018 | 11/7/2018 | 11/8/2018 | P | PART |
Dave Hannah
|
|
|
Please call 30 minutes prior to inspection. Phone #: ###-#### Inspection requested via web by Chris Eby air seal ok
|
BLD-Wall Bracing | 11/7/2018 | 11/7/2018 | 11/7/2018 | P | PASS |
Dave Hannah
|
|
|
Please call 30 minutes prior to inspection. Phone #: ###-#### Inspection requested via web by Chris Eby
|
Plan Modification Accepted | | | 10/11/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 10/11/2018 | | 10/11/2018 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Foundation | 4/20/2018 | 4/23/2018 | 4/23/2018 | A | PASS |
Dave Hannah
|
|
|
Wall - Zach Phone #: ###-####
|
BLD-Foundation | 4/17/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
BLD-Footing | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | CANC |
Dave Hannah
|
|
|
Zack-pour wall in aft Phone #: ###-####
|
BLD-Footing | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | CANC |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
OVERRIDE | | | 4/2/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 3/20/2018 | 3/20/2018 | 4/2/2018 | | PASS |
Josh Bogle
|
|
|
1st done - see e-mail 3/27 to Ward for needed details
|
Routing - PLAN CHECK | 4/2/2018 | | 4/2/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 4/2/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 4/2/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 4/2/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/2/2018 | | DONE |
|
|
|
|
1st review completed | | | 3/27/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/20/2018 | | 3/27/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 3/20/2018 | | 3/23/2018 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (Zoning) | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Josh Bogle
|
|
|
took in as a level 2 to route to Mech
|
Application received | | 3/20/2018 | | | |
|
|
|
|