Print Statement | | | 3/15/2019 | | DONE |
|
|
|
Per Kim Harp with West Ada School district, a statement with their name was emailed over to her so the company could pay for the final value fees. See documents for emails (harp.kimberly@westada.org)
|
Print Statement | | | 3/14/2019 | | |
|
|
|
|
Print Statement | | | 2/14/2019 | | DONE |
|
|
|
|
Print Statement | | | 2/8/2019 | | DONE |
|
|
|
|
First Notice | | 1/14/2019 | 2/6/2019 | | DONE |
|
|
|
emailed in 306 for final value
|
Print Statement | | | 2/6/2019 | | DONE |
|
|
|
|
BLD-Final | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Jim Sly
|
|
|
Request for Final Occupancy. The last piece of panic hardware is currently being installed and should be complete by 2pm. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski OK for Perm. Occ.
|
Permanent Occupancy | | | 1/4/2019 | | DONE |
|
|
|
|
Temporary Occupancy | 1/3/2019 | 4/3/2019 | 1/3/2019 | | DONE |
Candy A. Nichols
|
|
|
|
Temporary Occupancy | 1/3/2019 | 4/3/2019 | 1/3/2019 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 1/2/2019 | 1/2/2019 | 1/2/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Request for Life Safety Final inspection. Please contact Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Other | 1/2/2019 | 1/2/2019 | 1/2/2019 | P | CANC |
Jim Sly
|
|
|
Life and Safety inspection request. Fire alarm final is this morning. I''m thinking that we could just do this when fire alarm is complete. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Final | 1/2/2019 | 1/2/2019 | 1/2/2019 | P | PART |
Jim Sly
|
|
|
OK for Temp. Occ. OK for Perm. Occ. when Panic Hardware is installed on Select classroom Exterior Exit Door.
|
PubWorks Occupancy Approval | 12/21/2018 | 12/21/2018 | 12/21/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Conference | 12/19/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Jim Sly
|
|
|
Building walk through prior to final. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Conference | 11/28/2018 | 11/29/2018 | 11/29/2018 | P | DEFR |
Mike Jordan
|
|
|
Request for project walk through and occupancy requirements forthcoming. Please try to stop by after 1pm due to meetings. Call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 11/14/2018 | 11/14/2018 | 11/14/2018 | A | PASS |
Jim Sly
|
|
|
Fire walls and lid inspections for hallway, classrooms and bathrooms. Please contact Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 11/5/2018 | 11/5/2018 | 11/5/2018 | A | DONE |
Jim Sly
|
|
|
Final screw pattern inspection request on wood sheeting inside the gym. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | PART |
Jim Sly
|
|
|
Screw pattern inspection request for the north wall of the gym. This is along grid line 5 between grids A and B. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski OK
|
BLD-Framing/Rough-in | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PASS |
Jim Sly
|
|
|
Screw pattern inspection request along west wall of the gym. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Energy code compliance | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PART |
Jim Sly
|
|
|
Fire lid inspection for the bathrooms, hallway, and classrooms. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Framing/Rough-in | 10/23/2018 | 10/23/2018 | 10/23/2018 | A | PART |
Jim Sly
|
|
|
Request for wall sheeting screw pattern inspection in the gym. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski 12 foot section in S. E. corner.......OK.
|
BLD-Conference | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | DONE |
Jim Sly
|
|
|
Request for consult with Plumbing Contractor and Architect this afternoon. Please call Dan to confirm what time works best. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Energy code compliance | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | PART |
Jim Sly
|
|
|
Inspection of Fire Lid request for rooms and hallway south of grid 3. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski Fix ceiling penitrations built wit dissimilar materials.
|
BLD-Other | 10/4/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Jim Sly
|
|
|
Spray applied fire proofing on columns. (grid line C between 3-5) Phone #: ###-#### Inspection requested via web by Scott Hilbert 5 columns......MTI inspected.
|
BLD-Other | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PART |
Jim Sly
|
|
|
Above ceiling fire taping. Phone #: ###-#### Inspection requested via web by Scott Hilbert Select rooms........
|
BLD-Energy code compliance | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PART |
Jim Sly
|
|
|
Insulation and vapor barrier Phone #: ###-#### Inspection requested via web by Scott Hilbert Select area......
|
BLD-Other | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Jim Sly
|
|
|
Shear wall screw inspection Phone #: ###-#### Inspection requested via web by Scott Hilbert
|
OVERRIDE | | | 10/2/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 9/25/2018 | 9/25/2018 | 10/2/2018 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - Plan Mod Pioneer Elementary
|
CHANGE STATUS TO (ISS) | | | 10/2/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/2/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/2/2018 | | 10/2/2018 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 10/2/2018 | | DONE |
|
|
|
Plan Mod Approved
DO Not ReIssue (plan mod fees due)
|
Routing - PLAN CHECK | 9/26/2018 | | 10/1/2018 | | FAIL |
Julie Romig
|
|
|
Need Form 310 Special Inspections for Spray Applied Fireproofing material.
|
Plan Modification Accepted | | | 9/25/2018 | | DONE |
|
|
|
Use spray applied fireproofing per UL X771 1-hour assembly in place of gypsum board 1-hour assembly (OL X528) at 3 locations
|
BLD-Framing/Rough-in | 9/21/2018 | 9/21/2018 | 9/21/2018 | A | PART |
Jim Sly
|
|
|
Request for fire lid inspection along grid 1 between classroom entry doors 110B and 103B. This alcove is exterior fire lid. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski OK
|
BLD-Framing/Rough-in | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PART |
Jim Sly
|
|
|
Inspection of encapsulated columns requested. Columns along grid 2 and the intersection of grids 5/B are ready. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski Above items......OK.
|
BLD-Other | 9/17/2018 | 9/17/2018 | 9/17/2018 | P | DONE |
Jim Sly
|
|
|
Air Barrier inspection request. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski 90 percent complete. MTI providing special inspections.
|
BLD-Framing/Rough-in | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | DONE |
Jim Sly
|
|
|
Consult request for fire ratings and column encapsulation. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski Defer to Architect of record.
|
BLD-Framing/Rough-in | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | PART |
Jim Sly
|
|
|
Exterior DensGlas screw pattern inspection request. Please call Dan with questions. MTI was out yesterday looking at the same thing Phone #: ###-#### Inspection requested via web by Dan Koski Gym Ok pending MTI special insp.and approval.
|
BLD-Framing/Rough-in | 8/22/2018 | 8/23/2018 | 8/23/2018 | A | PART |
Jim Sly
|
|
|
Request for framing inspection on Gym and Classroom exterior walls. Please call Dan with any questions. Special inspection is scheduled as well. Phone #: ###-#### Inspection requested via web by Dan Koski Classroom and Gym Exterior walls and hold downs OK. MTI on site for welded connections.
|
BLD-Other | 7/31/2018 | 7/31/2018 | 7/31/2018 | P | DEFR |
Jim Sly
|
|
|
Request for inspection of Seepage bed before fabric and rock install. The Land Group is scheduled to come out as well. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski Advised contr. to Call Public Works.
|
BLD-Framing/Rough-in | 7/30/2018 | 7/31/2018 | 7/31/2018 | A | PART |
Jim Sly
|
|
|
Request for install procedures, proper insulation, and overall framing request. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Other | 7/26/2018 | 7/27/2018 | 7/26/2018 | P | PASS |
Jim Sly
|
|
|
Rebar and Vapor Barrier inspection request for the remainder of the building slab. This will complete our interior slab from grid lines A-D and 1-5. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski OK pending MTI special inspection, tests and approvals.
|
BLD-Other | 7/26/2018 | 7/26/2018 | 7/26/2018 | A | PART |
Jim Sly
|
|
|
Masonry rebar inspection request for the trash enclosure. Grouting this at 12pm. We will have MTI on site to take samples and check rebar as well. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski OK pending MTI special inspections, tests and approvals.
|
BLD-Concrete | 7/20/2018 | 7/20/2018 | 7/20/2018 | A | PART |
Jim Sly
|
|
|
Gym slab rebar and vapor barrier inspection request. The slab is scheduled to place next Monday. PM inspection is fine as well the area ready at any time. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski Slab OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Brandon Shaw
|
|
|
Rebar inspection for spread footings along grid C and grids 4;5. Trash enclosure rebar in the footing requested as well. MTI is scheduled for special inspection as well.
|
BLD-Foundation | 7/13/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Jim Sly
|
|
|
Request for inspection on the rebar in the concrete stem walls. Perimeter stem walls and gym walls being placed this afternoon. Grids 1-5 and A-D. Please call Dan with any concerns. Phone #: ###-#### Inspection requested via web by Dan Koski OK .....Pending MTI special inspections, tests and approvals.
|
BLD-Footing | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | PASS |
Jim Sly
|
|
|
Rebar inspection request for the footing placement scheduled this afternoon. Grids A-D, and 1-5. Please call Dan with any questions. Thanks Phone #: ###-#### Inspection requested via web by Dan Koski OK Pending MTI special inspections, Tests and Approvals.
|
BLD-Conference | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | DONE |
Jim Sly
|
|
|
Pioneer Elementary overview and plans for the project. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
|
Issue PAID IN FULL permit | | | 6/13/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/13/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/11/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 4/26/2018 | 4/26/2018 | 6/11/2018 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 3rd Rec'd - **Expedite** - 502 Pioneer Elementary
|
Routing - PLAN CHECK | 6/8/2018 | | 6/11/2018 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 6/8/2018 | | 6/11/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/11/2018 | | DONE |
|
|
|
NEED - all met
RP
GC FORM - met
REVISED VALUE - met
|
Routing Off Site - STRUCTURAL | 5/25/2018 | | 6/7/2018 | | FAIL |
Julie Romig
|
|
|
Failed per ePlan
|
Routing - PUBLIC WORKS | 4/26/2018 | | 6/7/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 5/25/2018 | | 6/6/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - ELECTRICAL | 5/25/2018 | | 5/26/2018 | | PASS |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 5/9/2018 | 5/12/2018 | 5/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 4/26/2018 | 4/26/2018 | 5/9/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 4/26/2018 | | 5/9/2018 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 5/9/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 4/26/2018 | | 5/1/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - ELECTRICAL | 4/26/2018 | | 4/30/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Sewer Design | 4/26/2018 | | 4/27/2018 | | PASS |
DeAnn Brown
|
|
|
New building sewer connected to existing private 8-inch sewer pipeline. Connection to Boise City Sanitary Sewer at MH627H22.
|
Routing PW Solid Waste | 4/26/2018 | | 4/27/2018 | | PASS |
Evan Carpenter
|
|
|
|
Intake Approval | | | 4/26/2018 | | PASS |
|
|
|
|
Routing - PLUMBING | 4/26/2018 | | 4/26/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 4/26/2018 | | 4/26/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 4/26/2018 | | 4/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/26/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/26/2018 | | DONE |
|
|
|
|
Routing PW Drainage | 4/26/2018 | | 4/26/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 4/26/2018 | | 4/26/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - MECHANICAL | 4/26/2018 | | 4/26/2018 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 4/26/2018 | | 4/26/2018 | | PASS |
Andy J. Long
|
|
|
ESC site map and plan narrative approved. RP to be desiganted by Beniton Construction, required before permit issue. Site preparation inspection is required.
|
Intake Approval | | | 4/16/2018 | | FAIL |
Michael Hanson
|
|
|
Missing completed and signed #304 form. MDH
|
Application received | | | 4/6/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 6 2018 12:44PM
|