BLD-Blower Door Test Results | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | DONE |
Tell Riley
|
|
|
duplex
4.49 ACH 50 1001 cfm @ 50 pa
4.34 ACH 50 934 cfm @ 50 pa
|
BLD-Final | 9/6/2019 | 9/9/2019 | 9/9/2019 | A | PASS |
Tell Riley
|
|
|
Barb Phone #: ###-####//corrections made//
|
DOC - Permit Finaled | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | FAIL |
Tell Riley
|
|
|
Barb Phone #: ###-####//need blower door test//seal penetrations in garage/house separation wall//add smoke detector to room in 9010//
|
BLD-Aging Inspection | 8/28/2019 | 8/28/2019 | 8/28/2019 | | PASS |
Tell Riley
|
|
|
Expires: 10/13/19
|
BLD-Energy code compliance | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 4/5/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Jim Sly
|
|
|
Barb Phone #: ###-####
|
BLD-Wall Bracing | 9/25/2018 | 9/26/2018 | 9/26/2018 | A | PASS |
Jim Sly
|
|
|
Barb Phone #: ###-#### 1st story walls between units have been built to townhouse standards.
|
BLD-Other | 9/20/2018 | 9/21/2018 | 9/21/2018 | A | PASS |
Jim Sly
|
|
|
Aaron-party wall inspect Phone #: ###-####
|
BLD-Foundation | 7/5/2018 | 7/5/2018 | 7/5/2018 | P | PASS |
Jim Sly
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Jim Sly
|
|
|
Eric-duplex Phone #: ###-####
|
OVERRIDE | | | 6/7/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 5/17/2018 | 5/17/2018 | 6/7/2018 | | DONE |
Rob Patrick
|
|
|
6/5 sfd L2 ePlan...5/24 FAILED: Manual J and beam on sheet 6 doesn't pass sizing.
|
Routing - MECHANICAL | 6/7/2018 | | 6/7/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 6/7/2018 | | 6/7/2018 | | PASS |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 6/7/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 6/7/2018 | | DONE |
|
|
|
|
Telephone call | | | 6/7/2018 | | DONE |
|
|
|
called ACHD talked to Mitch he said with a SFD being demo'd and a now a new duplex going in impact fees for them are $119.00.
he got these fees because he took a duplex fee $3076.00 and subtracted the SFD (no on tax) fee $2957.00 so the new total is $119.00
|
Inspection Record Card- Bld | | | 6/7/2018 | | DONE |
|
|
|
|
Telephone call | | | 6/7/2018 | | DONE |
|
|
|
called Larry and let him know permit is ready and fee due
|
Issue PAID IN FULL permit | | | 6/7/2018 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/29/2018 | | 6/4/2018 | | FAIL |
Troy James
|
|
|
Corrections have not been made. Emailed air systems again.
|
Plan Reviewer's activity | | | 5/29/2018 | | |
|
|
|
5/29...Took 2 copies of new Manual J and put them on Troy's desk.
|
Plan resubmittals received | | | 5/29/2018 | | DONE |
|
|
|
resubmittals recieved 2 sets of manual J's-took to Rob P
|
1st review completed | | | 5/24/2018 | | FAIL |
Rob Patrick
|
|
|
Manual J failed; Beam on sheet 6 doesn't pass, needs reviewed.
|
Routing - PLAN CHECK | 5/23/2018 | | 5/24/2018 | | FAIL |
Rob Patrick
|
|
|
Manual J failed; Beam on sheet 6 doesn't pass, needs reviewed.
|
Routing - MECHANICAL | 5/22/2018 | | 5/23/2018 | | FAIL |
Troy James
|
|
|
emailed corrections to air systems
|
Routing - PLANNING | | | 5/22/2018 | | PASS |
|
|
|
Prior to final occupancy an undergroud sprinkler system shall be installed.
|
Routing - PUBLIC WORKS | 5/17/2018 | | 5/21/2018 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 5/17/2018 | 5/20/2018 | 5/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 5/17/2018 | | 5/18/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/17/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/17/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/17/2018 | | DONE |
|
|
|
|
Application received | | 5/17/2018 | | | |
|
|
|
|