BLD-Final | 9/26/2019 | 9/27/2019 | 9/27/2019 | P | CANC |
Brandon Shaw
|
|
|
Bill Phone #: ###-####
|
FIRE-Final Inspection | 9/26/2019 | 9/27/2019 | 9/27/2019 | P | FAIL |
Jim Page
|
|
|
Provide fire sprinkler in area as discussed outside of phone room. Items are stored closer than 18 inches to ceiling, per NFPA13, section 8.5.6, a minimum of 18 inches of clearance is required from bottom of deflector to top storage.
Bill Phone #: ###-####
|
BLD-Aging Inspection | 7/15/2019 | 7/15/2019 | 7/16/2019 | | DEFR |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | DEFR |
Brandon Shaw
|
|
|
|
Issue PAID IN FULL permit | | | 8/29/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/29/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/29/2018 | | DONE |
|
|
|
|
Plan assigned to (RMH) | 6/5/2018 | 6/5/2018 | 6/6/2018 | | PASS |
Ron Hill
|
|
|
6/06 L1 Advantage Solutions Suite #200**
|
1st review completed | | | 6/6/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2018 | | DONE |
|
|
|
PAUL@EKCCONSTRUCTION.COM
MET
need
GC
Rev Cert of Val
|
Routing - PLAN CHECK | 5/31/2018 | | 6/6/2018 | | PASS |
Javier Guzman
|
|
|
|
Plan assigned to (JG) | 5/31/2018 | 5/31/2018 | 6/5/2018 | | DEFR |
Javier Guzman
|
|
|
6/06 L1 Advantage Solutions Suite #200**
|
Routing PW Flood Plain | 5/31/2018 | | 6/1/2018 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR in file. No floodplain review required. JCT
|
Routing - Addressing | 5/31/2018 | | 5/31/2018 | | PASS |
Doug Chausow
|
|
|
Suite 200
|
Routing - PUBLIC WORKS | 5/31/2018 | | 5/31/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 5/31/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 5/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 30 2018 9:09AM
|