BLD-Final | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by John Johnston
|
DOC - Permit Finaled | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/8/2019 | 2/8/2019 | 2/12/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Wall cover | 9/25/2018 | 9/26/2018 | 9/26/2018 | A | PASS |
Jim Storey
|
|
|
Insulation inspection Phone #: ###-#### Inspection requested via web by John Johnston
|
BLD-Energy code compliance | 9/25/2018 | 9/26/2018 | 9/25/2018 | A | CANC |
Tony Young
|
|
|
Insulation inspection Phone #: ###-#### >> Inspection requested via web by John Johnston Inspection cancelled from web by: John Johnston
|
BLD-Framing/Rough-in | 9/20/2018 | 9/21/2018 | 9/21/2018 | A | PASS |
Tony Young
|
|
|
Call Jim Kirk, ###-####, if any questions. Phone #: ###-#### Inspection requested via web by John Johnston
|
BLD-Wall Bracing | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | PASS |
Tony Young
|
|
|
shearing Phone #: ###-#### Inspection requested via web by John Johnston
|
BLD-Footing | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by John Johnston
|
BLD-Footing | 7/26/2018 | 7/27/2018 | 7/27/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by John Johnston,, need plans
|
BLD-Footing | 7/26/2018 | 7/27/2018 | 7/27/2018 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by John Johnston,, 1st footing ok
|
PubWorks Subgrade Approval | 7/27/2018 | 7/27/2018 | 7/27/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by John Johnston,, needs soils 1st
|
BLD-Conference | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | NR |
Tony Young
|
|
|
Please call ahead // Dan Phone #: ###-####, wanted a footing inspection,, needs soils approved 1st
|
OVERRIDE | | | 6/22/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/22/2018 | | DONE |
|
|
|
|
Telephone call | | | 6/22/2018 | | DONE |
|
|
|
Called John to advise permit is ready pending RP and gave fees due
|
Permit Ready to Issue | | | 6/22/2018 | | DONE |
|
|
|
Need
RP - met
|
Plan assigned to (JAB) Josh | 6/20/2018 | 6/20/2018 | 6/21/2018 | | PASS |
Josh Bogle
|
|
|
due 6/26 - Hillside addition
|
Routing - PLAN CHECK | 6/20/2018 | | 6/21/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | 6/20/2018 | | 6/21/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. GC is certified RP.
|
Routing PW Grading-Hillside | 6/20/2018 | | 6/21/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
|
1st review completed | | | 6/21/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 6/21/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 6/21/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2018 | | DONE |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 6/20/2018 | 6/20/2018 | 6/20/2018 | P | PASS |
Josh Bogle
|
|
|
took in as a level two, routed to Hillside & ESC
|
Routing Walk-In (Zoning) | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | PASS |
Jeff Lowe
|
|
|
pending approval of hillside
|
Routing Walk-In (BLD) | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | FAIL |
Josh Bogle
|
|
|
Hillside - WUI - lacked needed details
|
Routing - PLAN CHECK | 6/12/2018 | | 6/12/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 6/12/2018 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 6/12/2018 | | | |
|
|
|
|