BLD-Final | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 3/1/2019 | 3/1/2019 | 3/1/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 3/1/2019 | 3/1/2019 | 3/1/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.4
|
PubWorks Occupancy Approval | 2/28/2019 | 2/28/2019 | 2/28/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 2/26/2019 | 2/26/2019 | 2/26/2019 | P | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 12/26/2018 | 12/27/2018 | 12/27/2018 | A | PASS |
Brandon Shaw
|
|
|
Shaer corrections SAT, see latter from Engineer of record in Documents tab...
|
BLD-Framing/Rough-in | 12/14/2018 | 12/17/2018 | 12/17/2018 | A | PASS |
Brandon Shaw
|
|
|
Approved revised plans on site... New hold downs and floor to floor straps to be completely installed by Energy inspection... OK to insulate...
|
BLD-Framing/Rough-in | 12/7/2018 | 12/7/2018 | 12/7/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Other | 12/5/2018 | 12/6/2018 | 12/6/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit...
|
Plan Modification Accepted | | | 11/27/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 11/27/2018 | | 11/27/2018 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 11/14/2018 | 11/14/2018 | 11/14/2018 | P | PART |
Brandon Shaw
|
|
|
Work in progress... Need revised Engineering submitted for review for omission of Strong Wall Panels, kitchen nook. Beam to replace Panels with floor trusses to be perpendicular or paralle to beam?
|
BLD-Wall Bracing | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | CANC |
Brandon Shaw
|
|
|
Need current revised approved plans... Two city sets on site, with wall brace, floor and roof drag truss Engineering not matching...
|
BLD-Foundation | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 10/4/2018 | 10/4/2018 | 10/4/2018 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell Inspection cancelled via mobile web on Thursday, October 04, 2018.
|
BLD-Footing | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | NR |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
OVERRIDE | | | 9/26/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 9/6/2018 | 9/6/2018 | 9/26/2018 | | DONE |
Brian McGowan
|
|
|
plan mod
|
Routing - PLAN CHECK | 9/6/2018 | | 9/26/2018 | | PASS |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/26/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE (fees due)
|
CHANGE STATUS TO (ISS) | | | 9/26/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/26/2018 | | DONE |
|
|
|
|
PubWorks Subgrade Approval | 9/6/2018 | 9/6/2018 | 9/6/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Plan Modification Accepted | | | 9/6/2018 | | DONE |
|
|
|
started workflow for plan mod to enclose open-to-below area above great room for second floor bonus room.
|
Issue PAID IN FULL permit | | | 8/23/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/7/2018 | | |
|
|
|
|
Routing - FIRE | 8/7/2018 | 8/7/2018 | 8/7/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (BJM) | 6/20/2018 | 6/20/2018 | 8/7/2018 | | DONE |
Brian McGowan
|
|
|
2nd review complete. 1st Review Complete 7-9 sfd L2 ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 8/7/2018 | | DONE |
|
|
|
met
|
Routing - FIRE | 7/25/2018 | 7/25/2018 | 7/25/2018 | | FAIL |
Tim Frost
|
|
|
Previous comment was not addressed
|
Routing - PLAN CHECK | 7/25/2018 | | 7/25/2018 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 7/9/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/20/2018 | | 7/9/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - Erosion and Sediment | 6/20/2018 | | 7/9/2018 | | PASS |
Michael Zawacki
|
|
|
Hillside lot. Site prep inspection required.
|
Routing - MECHANICAL | 6/20/2018 | | 6/25/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 6/20/2018 | 6/23/2018 | 6/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 6/20/2018 | 6/20/2018 | 6/21/2018 | | FAIL |
Tim Frost
|
|
|
7/09 New SFH ePlan
Fire flow information is missing.
|
Routing PW Grading-Hillside | 6/20/2018 | | 6/20/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/20/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 6/20/2018 | | 6/20/2018 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 6/20/2018 | | 6/20/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2018 | | 6/20/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 6/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2018 11:13AM
|