BLD-Final | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Jim Sly
|
|
|
Adam Phone #: ###-#### Blower Door 3.55
|
DOC - Permit Finaled | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Jim Storey
|
|
|
Adam-energy signed off yesterday but frame was not-can you email Adam the results Phone #: ###-####
|
BLD-Energy code compliance | 10/4/2018 | 10/4/2018 | 10/4/2018 | P | PASS |
Brandon Shaw
|
|
|
Correction SAT...
|
BLD-Framing/Rough-in | 9/20/2018 | 9/21/2018 | 9/21/2018 | P | PART |
Jim Storey
|
|
|
adam Phone #: ###-#### blk and nail hangers to box 1 girder// b1 and b2 missing center bearing point/ ok to insulate// sheer ok
|
BLD-Wall Bracing | 8/24/2018 | 8/27/2018 | 8/27/2018 | P | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
BLD-Foundation | 7/18/2018 | 7/19/2018 | 7/19/2018 | P | NR |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell wip
|
BLD-Footing | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
Issue PAID IN FULL permit | | | 7/13/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/12/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/12/2018 | | DONE |
|
|
|
|
Telephone call | | | 7/12/2018 | | DONE |
|
|
|
Brittany will call since she's calling on 2 other permits for Eaglewood
|
Telephone call | | | 7/12/2018 | | DONE |
|
|
|
Spoke with Josh informing him that this permit is ready and the fee amount due
|
Routing - PLAN CHECK | 6/29/2018 | | 7/12/2018 | | PASS |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 7/12/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/12/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 6/22/2018 | | 7/12/2018 | | DONE |
Michael Hanson
|
|
|
07/05 sfd L1 Paper. 1st review completed - Energy and code year incorrect. MDH
|
Routing - PLANNING | 7/9/2018 | | 7/9/2018 | | PASS |
Jeff Lowe
|
|
|
driveway shall be no wider than 33-feet
|
Plan resubmittals received | | | 7/3/2018 | | DONE |
|
|
|
resubmittals recevied 2 sets of sheets A1.1, A2.1, A3.1, A3.2, A3.3, A3.4, A3.5, A3.6, A4.1, A5.1, A5.2, A6.1 & A6.2-took to Michael H
|
Routing - PLAN CHECK | 6/28/2018 | | 6/29/2018 | | FAIL |
Michael Hanson
|
|
|
Energy and code year incorrect. MDH
|
1st review completed | | | 6/29/2018 | | FAIL |
Michael Hanson
|
|
|
Energy and code year incorrect. MDH
|
Routing - MECHANICAL | 6/26/2018 | | 6/28/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 6/25/2018 | | 6/26/2018 | | FAIL |
Jeff Lowe
|
|
|
plans okay - FAIL until issuance of satisfacion letter. driveway to be no wider than 33-feet.
|
Route to Impact Fee Review | 6/22/2018 | 6/25/2018 | 6/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 6/22/2018 | | 6/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/22/2018 | | 6/25/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/22/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/22/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/22/2018 | | DONE |
|
|
|
|
Application received | | 6/22/2018 | | | |
|
|
|
|