Permit Information
Permit NumberBLD18-02510
StatusFinaled
Name RRC CONTRACTORS
Site Address 999 W MAIN ST Unit: 103
Project NameFirenza
Customer Number 
ePlanReviewYes
Description
(FIRENZA – 1ST STORY – SOUTHEAST CORNER) (DRH18-00244) The fire sprinkler system is used for high rise and for fire area. To convert a 2,644 square foot area formerly used as an office into a pizza restaurant. The total area of the restaurant will be 3,569 square feet (2,644 square feet interior and 925 square feet exterior patios). Work is to include interior nonbearing walls, wall furring, half-height walls, interior doors, two new exterior overhead glass doors with tube steel beams and columns to resist out-of-plane lateral loads, guard rails, dining booths, tables and chairs, fixed benches, drink dispensers, a 95 square foot walk-in cooler, kitchen equipment, a gas fired pizza oven that weighs about 7,000 pounds, a Type I grease hood and horizontal duct system, a stacked washer and dryer, suspended acoustical ceilings, gypsum board ceilings and soffits, millwork, and finishes. Special Inspection is required for welding and for anchors post-installed in hardened concrete. The toilet rooms on the 1st story were upgraded to be accessible to the disabled under permit BLD18-01334. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/16/20194/12/2019 DONE
This permit finaled on the web by derek cooper
Third Notice 3/12/20194/11/2019 DONE
mailed 4-12-19
Third Notice 2/11/20193/7/2019 DONE
mailed 3-11
Second Notice 1/18/20192/6/2019 DONE
mailed 2-11-19
First Notice 12/16/20181/8/2019 DONE
mailed 1-11-19
BLD-Final12/6/201812/7/201812/6/2018APASS
DetailsDave Hannah
PER DAVE H
FIRE-Final Inspection12/6/201812/6/201812/6/2018PPASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire exitnguishers are in place with current inspection tags, hood fire suppresion system for pizza oven is not required per conversation with Adele Schaffeld-Griffin, Assistant Building Official. Final life fire safety inspection for area of work complete.

Please call before arrival. Thank you Phone #: ###-#### Inspection requested via web by David Sferle
Zoning Approval12/6/201812/6/201812/6/2018 PASS
DetailsKatelyn Menuge
Permanent Occupancy  12/6/2018 DONE
BLD-Ceiling Grid Inspection12/4/201812/4/201812/4/2018PPASS
DetailsDave Hannah
Please call before arrival. Phone #: ###-#### Inspection requested via web by David Sferle
FIRE-Conference12/3/201812/3/201812/3/2018PDONE
DetailsTroy Cobbley
We discussed lowering the ceiling mounted strobes to the lowere "clouds" and fire extinguisher placement.

Phone #: ###-#### Inspection requested via web by David Sferle
BLD-Other11/28/201811/28/201811/28/2018PDONE
DetailsDave Hannah
Please call before arrival. Question about floor sink fire sealing. Phone #: ###-#### Inspection requested via web by David Sferle
BLD-Ceiling Grid Inspection11/26/201811/26/201811/28/2018PPEND
DetailsDave Hannah
Please call before arrival. Id like to have a consultation on existing grid. Thank you. Phone #: ###-#### Inspection requested via web by David Sferle
BLD-Ceiling Grid Inspection11/21/201811/21/201811/21/2018PCANC
DetailsMike Jordan
Please contact me upon arrival, this inspection is for kitchen area only. Need consultation for existing ceiling at front of house.

Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald. Kitchen area ok.
BLD-Framing/Rough-in10/31/201810/31/201810/31/2018PPASS
DetailsDave Hannah
Please call before arrival. Thank you Phone #: ###-#### Inspection requested via web by David Sferle
BLD-Framing/Rough-in10/25/201810/26/201810/26/2018ANR
DetailsDave Hannah
Please call before arrival. Located on the first floor south east corner. Phone #: ###-#### Inspection requested via web by David Sferle needs other trades and fire stopping on plumbing thru floor
Plan assigned to (CJW)7/23/20187/23/20189/18/2018 PASS
DetailsCarl Westfall
(2nd done) 08/08/18 (L3 - 15 days) (ePlan - 27 sheets) Firenza
PLANS/APPL TAKEN TO FRONT DESK  9/18/2018 DONE
Permit Ready to Issue  9/18/2018 DONE
Need
GC Form
Revised Cert of Value
Print Occupancy Form  9/18/2018 DONE
Issue PAID IN FULL permit  9/18/2018 DONE
Routing - MECHANICAL9/14/2018 9/17/2018 PASS
DetailsTroy James
Routing - PLUMBING9/14/2018 9/17/2018 PASS
DetailsBill VanDegrift
per ISPC
Routing - PLAN CHECK9/13/2018 9/14/2018 PASS
DetailsCarl Westfall
Drawings approved after 2nd review
Plan resubmittals received  9/13/2018 DONE
Route to Impact Fee Review8/22/20188/25/20188/23/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  8/22/2018 DONE
Plan resubmittals requested  8/22/2018 DONE
Routing - PLAN CHECK7/23/2018 8/22/2018 FAIL
DetailsCarl Westfall
Completed the 1st review. Sent the applicant a copy of the plan review report. Explained it to him on the phone.
Routing - FIRE7/23/20187/23/20188/14/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - MECHANICAL7/23/2018 7/27/2018 FAIL
DetailsTroy James
Talked to engineer on phone
Routing - PLUMBING7/23/2018 7/24/2018 PASS
DetailsBill VanDegrift
Routing PW Environmental7/23/2018 7/24/2018 PASS
DetailsRick Christenson
Routing - Design Review7/23/2018 7/24/2018 PASS
DetailsAndrea Tuning
Routing - PLANNING7/23/2018 7/23/2018 PASS
DetailsDavid Moser
Routing - Addressing7/23/2018 7/23/2018 PASS
DetailsDoug Chausow
Suite 103
Routing - PUBLIC WORKS7/23/2018 7/23/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment7/23/2018 7/23/2018 PASS
DetailsMichael Zawacki
Interior tenant improvement, no ESC waiver or plan required. If material or staging takes place outside than a waiver detailing storage plans will be required.
Intake Approval  7/19/2018 PASS
Plan Reviewer's activity  7/18/2018 PASS
DetailsCarl Westfall
Plan intake review approved.

In response to the redlines you have provided for the Major T.I. Submittal Checklist, the changes are as follows:

1.) The portable fire extinguishers have been added to sheet A-3.0 and the new sheet uploaded.

2.) The structural evaluation of the floor for the weight of the pizza oven has been uploaded to the documents folder as "2018-4-24 Ground Floor Evaluation".

3.) Under the "Accessibility Inside the Building" section, we have removed an existing entry that did not meet accessibility requirements (called out as note #5 on sheet A-2.0) and replaced with a new door (shown as note #19 on sheet A-3.0). The restrooms upgrades are being provided by the building owner (Oppenheimer Development), and are not a part of this submittal package.

4.) Under the "Mechanical Plans" section, here is an explanation from the engineer on where the make-up air is coming from:

"We are supplying 6600 CFM of air into the space with 5 mixing boxes and exhausting 1,300 CFM (300 CFM for the pizza oven and 1000 CFM for EF-2/general exhaust) . The remainder of the air returns to the main air handler via the return air plenum."

If you have any further questions or concerns, I will be out of the office for the remainder of the week. However, Jerrod Wallgren in our office will be happy to assist. His email is: jwallgren@jgt-architecture.com

Thank you, and have a good day!

Aaron M. Randell
Intake Approval  7/16/2018 FAIL
(7-16-18) Refer to the circled items in the plan intake checklist. Resolve each item as directed. CJW
Intake Approval  7/14/2018 FAIL
DetailsCarl Westfall
(7-14-18) A plan intake review was not done. The ePlanReview standards were not followed. Review the submission standards and follow them. Each drawing sheet is required to be uploaded as an individual file in the drawings folder. The file name for each drawing shall be the same name as listed in the Drawing Index on Sheet A-1.0. Make sure all other standards are also followed.
Application received  7/13/2018 DONE
Application submitted via PDS Online on Jul 13 2018 3:02PM