First Notice | | 1/6/2019 | 12/28/2018 | | DONE |
|
|
|
sent in 12-26-18
|
Permanent Occupancy | | | 12/27/2018 | | DONE |
|
|
|
|
Meeting | | | 12/26/2018 | | DONE |
|
|
|
cameron mailed in final values on 306 form
|
Print Statement | | | 12/26/2018 | | DONE |
|
|
|
|
BLD-Final | 12/17/2018 | 12/18/2018 | 12/18/2018 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington
|
FIRE-Final Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire exitnguishers are placed with current inspection tags. Sticker above door will be changed from doors to remain unlocked during business hours to "Door to remain unlocked while building is occupied" before building final. Final life fire safety inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Final | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need Electrical and Fire/Life finals...
|
BLD-Ceiling Grid Inspection | 12/4/2018 | 12/5/2018 | 12/5/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Framing/Rough-in | 11/5/2018 | 11/5/2018 | 11/5/2018 | A | PASS |
Jim Storey
|
|
|
Framing inspection at the new office that was added. It is at the front of the building space. Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Framing/Rough-in | 11/1/2018 | 11/2/2018 | 11/2/2018 | P | NH |
Jim Storey
|
|
|
Framing inspection for the office at the front of the building that was added to job. Phone #: ###-#### Inspection requested via web by Sean Worthington no access
|
Print Occupancy Form | | | 10/29/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/29/2018 | | DONE |
|
|
|
revised
|
CHANGE STATUS TO (ISS) | | | 10/29/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/26/2018 | | DONE |
|
|
|
DO NOT ISSUE PLAN MOD
|
Plan assigned to (JG) | 10/22/2018 | 10/22/2018 | 10/25/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod Westmark Credit Union
|
Routing - PLAN CHECK | 10/24/2018 | | 10/25/2018 | | PASS |
Javier Guzman
|
|
|
|
Plan Modification Accepted | | | 10/22/2018 | | DONE |
|
|
|
what used to be a customer lounge and a storage room will now be converted into an office. Also rather than using the existing ceiling grin in the entry and the new office, new grid will be installed. The lighting fixtures and hvac grilles will be reused
|
BLD-Framing/Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington pending ele
|
Issue PAID IN FULL permit | | | 9/14/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/14/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/14/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/14/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/14/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/10/2018 | | DONE |
|
|
|
all met-NEED
GC FORM-met
REVISED VALUE-met
|
Plan assigned to (JG) | 8/3/2018 | 8/3/2018 | 9/8/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 8/16 L2 Westmark Credit Union T.I.ePlan
|
Routing - PLAN CHECK | 9/7/2018 | | 9/8/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/23/2018 | | 8/29/2018 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 8/22/2018 | 8/25/2018 | 8/22/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 8/22/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/3/2018 | | 8/22/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 8/3/2018 | | 8/3/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/3/2018 | | 8/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Drainage | 8/3/2018 | | 8/3/2018 | | PASS |
Brian Murphy
|
|
|
|
Intake Approval | | | 8/3/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 7/30/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Missing wall bracing detail. How are new interior walls secured?
|
Application received | | | 7/25/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 25 2018 1:55PM
|
Routing - Design Review | 8/3/2018 | | | | PASS |
KayCee Babb
|
|
|
per DRH18-00295
|