Third Notice | | 4/16/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19 with first follow up letter
|
First Follow up | | | 5/6/2019 | | DONE |
|
|
|
|
Third Notice | | 3/16/2019 | 4/11/2019 | | DONE |
|
|
|
mailed 4-12-19
|
Third Notice | | 2/12/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12
|
Second Notice | | 1/18/2019 | 2/7/2019 | | DONE |
|
|
|
mailed 2-11-19
|
First Notice | | 12/15/2018 | 1/8/2019 | | DONE |
|
|
|
mailed 1-11-19
|
Print Occupancy Form | | | 12/5/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/5/2018 | | DONE |
|
|
|
|
BLD-Final | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | PASS |
Jim Storey
|
|
|
Nicol Phone #: ###-####
|
BLD-Final | 11/28/2018 | 11/29/2018 | 11/29/2018 | P | PART |
Jim Storey
|
|
|
Nicol Phone #: ###-####tco pending counter
|
FIRE-Final Inspection | 11/27/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire exitnguisher is placed with a current inspection tag. Addressing on the sign board is temporary and permenant addressing will be installed when received.
Nicol Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/23/2018 | 11/23/2018 | 11/23/2018 | P | PASS |
Jim Storey
|
|
|
Nicol Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/19/2018 | 11/21/2018 | 11/21/2018 | A | FAIL |
Jim Storey
|
|
|
Nicol Phone #: ###-#### remove all tile and call for insp.
|
BLD-Framing/Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Brandon Shaw
|
|
|
Nicklo Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/29/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/29/2018 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 9/19/2018 | 9/19/2018 | 10/26/2018 | | PASS |
Joe Bruce
|
|
|
*(1st Rev Comp) 10/08 (L2) - Idaho Liquor Store (DR)
|
Routing - Design Review | 10/16/2018 | | 10/26/2018 | | PASS |
KayCee Babb
|
|
|
per CZC18-00245.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2018 | | DONE |
|
|
|
|
Meeting | | | 10/26/2018 | | DONE |
|
|
|
NYOUNG@WBTBC.COM
|
Routing - PLAN CHECK | 10/26/2018 | | 10/26/2018 | | PASS |
Joe Bruce
|
|
|
|
Permit Ready to Issue | | | 10/26/2018 | | DONE |
|
|
|
all met-NEED
GC-met
Rev cert of val-met
|
Plan resubmittals received | | | 10/16/2018 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 10/8/2018 | 10/11/2018 | 10/8/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 10/8/2018 | | FAIL |
Joe Bruce
|
|
|
Needs approval from Design Review for exterior modificaions. **JHB**
|
Routing - PLAN CHECK | 9/19/2018 | | 10/8/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 9/19/2018 | | 10/5/2018 | | PASS |
Joe Bruce
|
|
|
AHJ - Chris Holladay
|
Routing Off Site - C.D.H | 9/19/2018 | | 10/5/2018 | | PASS |
Joe Bruce
|
|
|
No Review Required
|
Routing - Addressing | 9/19/2018 | | 9/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/19/2018 | | 9/19/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 9/19/2018 | | 9/19/2018 | | FAIL |
KayCee Babb
|
|
|
Design Review is required for exterior alterations, including door modifications and new railing.
|
Intake Approval | | | 9/18/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 9/17/2018 | | FAIL |
Joe Bruce
|
|
|
1) Form #304 is missing owner information and signature.
2) Several plan sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block.
3) Cover sheet lists the incorrect Mechanical Code. Boise has adopted the 2012 IMC. Revise drawing.
4) Indicate the U-Value of door 107A to comply with the fenestration requirements of the IECC (min. 0.77).
|
Application received | | | 9/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 13 2018 4:54PM
|