BLD-Final | 5/13/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Dave Hannah
|
|
|
The HVAC inspection happened today after the pressure balance test was completed. Their inspector said he would have it signed off tomorrow morning. Thanks Phone #: ###-#### Inspection requested via web by Dustin Collins
|
DOC - Permit Finaled | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 1/29/2019 | 1/31/2019 | 1/31/2019 | A | PART |
Dave Hannah
|
|
|
Insulation will be completed on Wednesday. We will be ready for installation prior to cover Thursday morning. Thank you Phone #: ###-#### Inspection requested via web by Dustin Collins ok to cover all but for ceiling in front room
|
BLD-Framing/Rough-in | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Dustin Collins
|
Plan Modification Accepted | | | 1/23/2019 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 1/23/2019 | | 1/23/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Conference | 1/2/2019 | 1/2/2019 | 1/9/2019 | P | DONE |
Dave Hannah
|
|
|
concern about building materials not being cleaned up.
|
BLD-Wall Bracing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Hold downs and floor to floor straps to be installed before framing rough-in...
|
BLD-Other | 11/28/2018 | 11/28/2018 | 11/29/2018 | P | DONE |
Dave Hannah
|
|
|
Neighbors are concerned about the building materials/trash on the sidewalk/street.
|
BLD-Foundation | 11/9/2018 | 11/9/2018 | 11/10/2018 | P | PASS |
Dave Hannah
|
|
|
steam wall ... as late as possible // Kevin Phone #: ###-####
|
BLD-Foundation | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | NR |
Dave Hannah
|
|
|
stem wall // Kevin Phone #: ###-####
|
Plan Modification Accepted | | | 11/7/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 11/7/2018 | | 11/7/2018 | | FAIL |
Troy James
|
|
|
emailed corrections to dustin mori
|
Routing - MECHANICAL | 11/7/2018 | | 11/7/2018 | | PASS |
Troy James
|
|
|
|
BLD-Footing | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Dave Hannah
|
|
|
Kevin Phone #: ###-####
|
OVERRIDE | | | 11/5/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 10/23/2018 | 10/23/2018 | 11/5/2018 | | PASS |
Josh Bogle
|
|
|
10/29 remodel, paper - 1st done
|
Routing - PLAN CHECK | 11/5/2018 | | 11/5/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/5/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/5/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 11/5/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/5/2018 | | DONE |
|
|
|
|
Routing - MECHANICAL | 11/5/2018 | | 11/5/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 10/29/2018 | | 10/31/2018 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Bryan 10/31
|
1st review completed | | | 10/31/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 10/23/2018 | | 10/29/2018 | | FAIL |
Troy James
|
|
|
emailed corrections to western htg
|
Routing - Addressing | 10/23/2018 | | 10/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2018 | | 10/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 10/23/2018 | | 10/24/2018 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/23/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/23/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/23/2018 | | DONE |
|
|
|
no fees taken at intake
|
Application received | | 10/23/2018 | | | |
|
|
|
|