BLD-Final | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | PASS |
Tony Young
|
|
|
Please call when you want to perform inspection. I need to make sure that I am home to unlock the unit. Patrick Phone #: ###-#### Inspection requested via web by Patrick Scheffler
|
DOC - Permit Finaled | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Tony Young
|
|
|
|
Zoning Approval | 7/16/2019 | 7/16/2019 | 7/16/2019 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Energy code compliance | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | PASS |
Brandon Shaw
|
|
|
eric Phone #: ###-####
|
BLD-Framing/Rough-in | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Tony Young
|
|
|
Eric Phone #: ###-####
|
BLD-Wall Bracing | 3/20/2019 | 3/20/2019 | 3/20/2019 | P | PASS |
Brandon Shaw
|
|
|
Eric Phone #: ###-####
|
BLD-Foundation | 1/17/2019 | 1/18/2019 | 1/18/2019 | A | CANC |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
BLD-Foundation | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | PASS |
Brandon Shaw
|
|
|
steam wall // Eric Phone #: ###-####
|
BLD-Foundation | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | PASS |
Tony Young
|
|
|
Patrick Phone #: ###-####
|
BLD-Footing | 12/27/2018 | 12/28/2018 | 12/28/2018 | P | PASS |
Tony Young
|
|
|
Patrick Phone #: ###-####
|
OVERRIDE | | | 11/19/2018 | | |
|
|
|
|
Telephone call | | | 11/19/2018 | | DONE |
|
|
|
Left a message for Patrick informing permit is ready and the fee amount due for issuance
|
Issue PAID IN FULL permit | | | 11/19/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/19/2018 | | DONE |
|
|
|
STATED UNDER APPLICANT INFO OWNER IS ACTING AS GC
Need- ALL MET
GC Form(if parcel owner is GC)
RP (if parcel owner is not GC)
|
Plan assigned to (JAB) Josh | 11/13/2018 | 11/13/2018 | 11/16/2018 | | PASS |
Josh Bogle
|
|
|
11/9 ADU, paper - 1st done
|
Routing - PLAN CHECK | 11/16/2018 | | 11/16/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/16/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/16/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2018 | | DONE |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Josh Bogle
|
|
|
discussed resubmittals with Noelle
|
Plan resubmittals received | | | 11/15/2018 | | DONE |
|
|
|
one copie of sheets A0.0, A0.1, A1.1, A1.2, A1.3, A1.4 A2.1 and A2.2 . Taken to Josh
|
Plan assigned to (BJM) | 10/29/2018 | 10/29/2018 | 11/13/2018 | | DEFR |
Brian McGowan
|
|
|
11/9 adu L1 paper
|
Routing - PLAN CHECK | 11/1/2018 | | 11/13/2018 | | FAIL |
Josh Bogle
|
|
|
see e-mail 11-13
|
1st review completed | | | 11/13/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 10/30/2018 | | 11/1/2018 | | PASS |
Troy James
|
|
|
mechanical ventilation with energy star rated bath fan on a 24 hour time clock.
|
Route to Impact Fee Review | 10/30/2018 | 11/2/2018 | 10/31/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 10/29/2018 | | 10/30/2018 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 10/29/2018 | | 10/29/2018 | | PASS |
Doug Chausow
|
|
|
ADU Address: 2005 N 9th St
|
Routing - PUBLIC WORKS | 10/29/2018 | | 10/29/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/29/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/29/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/29/2018 | | DONE |
|
|
|
|
Application received | | 10/29/2018 | | | |
|
|
|
|