Permit Information
Permit NumberBLD18-03990
StatusIssued
Name LAYTON CONSTRUCTION
Site Address 111 W STATE ST
Project NameSt. Luke's Downtown Parking Ga
Customer Number 
ePlanReviewYes
Description
(ST LUKES DOWNTOWN PARKING GARAGE) Permit for the construction of a new 383,808 sq. ft. parking garage with two levels of enclosed below grade (95,479 sq. ft.) and 5 levels of open above grade parking (288,329 sq. ft.). This building is fully fire sprinklered for fire flow. with the enclosed garage required to be sprinklered as an enclosed parking garage. This building is fully fire sprinklered for fire flow. CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Concrete1/9/20201/10/20201/10/2020APEND
DetailsDave Hannah
Charlie Phone #: ###-#### ok with spec inspection
BLD-Foundation12/9/201912/9/201912/11/2019PPASS
DetailsDave Hannah
Charle Phone #: ###-#### ok after spec inspection sign offs
BLD-Concrete10/10/201910/11/201910/11/2019ACANC
DetailsJim Storey
Brian Phone #: ###-####
BLD-Other8/13/20198/13/20198/16/2019PPASS
DetailsDave Hannah
slab on deck level G //Brian Phone #: ###-####
BLD-Foundation7/17/20197/18/20197/18/2019PPASS
DetailsDave Hannah
Brian- foundation slab Phone #: ###-####
BLD-Concrete7/8/20197/8/20197/9/2019PPASS
DetailsDave Hannah
slab // brian Phone #: ###-####
BLD-Concrete7/1/20197/2/20197/2/2019APEND
DetailsDave Hannah
rebar in columns - gridline P15 // Brian Phone #: ###-####
BLD-Other6/27/20196/28/20196/28/2019ADEFR
DetailsMike Jordan
Brian- inspection for inwall rebar PCLINE Phone #: ###-####. Pending special inspection.
BLD-Concrete6/20/20196/21/20196/24/2019APASS
DetailsDave Hannah
rebar- Rid thin P15-Brian Phone #: ###-####
BLD-Foundation6/24/20196/25/20196/24/2019ACANC
DetailsDave Hannah
P D line- Brian Phone #: ###-####
BLD-Wall Bracing6/18/20196/19/20196/19/2019APART
DetailsBrandon Shaw
Pending Special Inspection...
rebar line PB
BLD-Foundation6/13/20196/14/20196/17/2019APASS
DetailsDave Hannah
PB line- Brian Phone #: ###-####
BLD-Foundation6/12/20196/13/20196/17/2019APASS
DetailsDave Hannah
rebar on gridline PA // Brian Phone #: ###-####
BLD-Other6/11/20196/12/20196/12/2019APEND
DetailsDave Hannah
Brian-shear wall rebar-grid line PB Phone #: ###-#### ok after spec final signoffs for placement of concrete
BLD-Wall Bracing6/5/20196/6/20196/6/2019APEND
DetailsDave Hannah
shear (pc grid line) // Brian Phone #: ###-#### ok after spec inspection sign off
BLD-Foundation6/3/20196/4/20196/4/2019APEND
DetailsDave Hannah
Brian- red line P15 going north to south Phone #: ###-#### ok after spec inspection sign off
BLD-Wall Bracing5/31/20196/3/20196/4/2019APEND
DetailsDave Hannah
Brian Phone #: ###-#### ok after spec inspection sign off
BLD-Other5/28/20195/29/20196/4/2019APEND
DetailsDave Hannah
concrete wall // Brian Phone #: ###-#### ok after spec inspection sign off
BLD-Footing5/30/20195/31/20196/4/2019APEND
DetailsDave Hannah
Brian-on grid line P15 ON THE EAST NE SIDE Phone #: ###-#### ok after spec inspection sign off
BLD-Foundation5/29/20195/30/20195/30/2019APEND
DetailsDave Hannah
Brian- inspection on grid line PD Phone #: ###-#### ok after spec insp sign offs
BLD-Other5/23/20195/24/20195/30/2019APEND
DetailsDave Hannah
Brian- column inspection- gridline PA North Wall Phone #: ###-#### ok after spec insp sign offs
BLD-Concrete5/22/20195/22/20195/30/2019APEND
DetailsDave Hannah
Brian-column line PA in the garage Phone #: ###-#### ok after spec insp sign offs
Extend Permit 90/180 days5/22/20195/22/20195/22/2019ACANC
DetailsDave Hannah
BLD-Footing5/20/20195/21/20195/22/2019APASS
DetailsDave Hannah
spread footer // Brian Phone #: ###-####
BLD-Other5/21/20195/22/20195/22/2019APART
DetailsDave Hannah
Brian-column line PA in the garage Phone #: ###-####
BLD-Wall Bracing5/16/20195/17/20195/20/2019PPEND
DetailsDave Hannah
wall cast in place, W side // Brian Phone #: ###-#### ok after spec inspection
BLD-Foundation5/15/20195/15/20195/16/2019PDONE
DetailsDave Hannah
rebar on N wall // Brian Phone #: ###-####
BLD-Foundation5/9/20195/10/20195/15/2019APART
DetailsDave Hannah
NW wall // Brian Phone #: ###-####
BLD-Foundation5/10/20195/13/20195/15/2019APART
DetailsDave Hannah
Ryan Phone #: ###-####
BLD-Foundation5/14/20195/15/20195/15/2019APART
DetailsDave Hannah
Brian Phone #: ###-####
BLD-Foundation5/2/20195/3/20195/6/2019ADONE
DetailsDave Hannah
west wall // Brian Phone #: ###-####
BLD-Framing/Rough-in5/3/20195/6/20195/6/2019ANR
DetailsDave Hannah
Brian Phone #: ###-####
Inspection Record Card- Bld  4/15/2019 DONE
Issue PAID IN FULL permit  4/15/2019 DONE
Permit Ready to Issue  3/15/2019 DONE
MET
Need
ACHD
Plan assigned to (CDM)11/9/201811/9/20183/14/2019 PASS
DetailsCarl D Madsen
St. Lukes Downtown Parking Garage
Routing - PLAN CHECK3/14/2019 3/14/2019 PASS
DetailsCarl D Madsen
Routing PW Drainage3/14/2019 3/14/2019 PASS
DetailsBrian Murphy
PLANS/APPL TAKEN TO FRONT DESK  3/14/2019 DONE
Routing PW Sewer Design2/20/2019 2/22/2019 PASS
DetailsDeAnn Brown
Connection to wet-line sewer is required and shown the corresponding grading permit (GRD18-00088).
Routing Off Site - STRUCTURAL2/20/2019 2/21/2019 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK2/20/2019 2/21/2019 PASS
DetailsCarl D Madsen
Pending issuance of the shoring permit and recording of easements.
Routing - Design Review2/20/2019 2/20/2019 PASS
DetailsJosh Wilson
Routing Off Site - STRUCTURAL1/22/2019 2/20/2019 FAIL
DetailsCarl D Madsen
KPFF
Routing - PLAN CHECK1/22/2019 2/9/2019 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL11/9/2018 2/9/2019 FAIL
DetailsCarl D Madsen
CH2M
Routing PW Drainage1/30/2019 1/30/2019 FAIL
DetailsBrian Murphy
NEED ACHD APDX J 80% NEED GRD18-00088 OKED
Routing - Design Review1/22/2019 1/25/2019 FAIL
DetailsJosh Wilson
Sheet AS101b- seating area required on 2nd Street per CUP18-00022
Routing - PLANNING1/22/2019 1/24/2019 PASS
DetailsCody Riddle
Routing - MECHANICAL1/22/2019 1/23/2019 PASS
DetailsTroy James
Route to Impact Fee Review12/20/201812/23/201812/28/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE11/9/201811/9/201812/19/2018 PASS
DetailsErika Akin
Attached comments to case
1st review completed  12/19/2018 DONE
Routing - PLAN CHECK11/9/2018 12/14/2018 FAIL
DetailsCarl D Madsen
Routing - Design Review11/9/2018 11/21/2018 FAIL
DetailsJosh Wilson
Sheet AS101b- seating area required on 2nd Street per CUP18-00022
Routing - MECHANICAL11/9/2018 11/20/2018 FAIL
DetailsTroy James
Routing - PLUMBING11/9/2018 11/16/2018 PASS
DetailsDan Ediger
Per ISPC/Plans. See redline note for DC assembly
Routing PW Sewer Design11/9/2018 11/16/2018 FAIL
DetailsDeAnn Brown
Mechanical and plumbing plans are low quality and unreadable. Please resubmit.
Routing PW Solid Waste11/9/2018 11/14/2018 PASS
DetailsEvan Carpenter
No new solid waste containers are proposed for this site.
Routing - Erosion and Sediment11/9/2018 11/14/2018 CANC
DetailsAndy J. Long
ESC for project already reviewed & approved. Site ESC permit to be covered by ESC18-01167
Routing - PUBLIC WORKS11/9/2018 11/13/2018 PASS
DetailsAngela Hardy
Routing - PLANNING11/9/2018 11/13/2018 FAIL
DetailsCody Riddle
Corrections/additional information required to demonstrate compliance with conditions #5 and 6 from the CUP. Emailed applicant.
Routing - Addressing11/9/2018 11/9/2018 PASS
DetailsDoug Chausow
Routing PW Street Lights11/9/2018 11/9/2018 PASS
DetailsTom Marshall
Intake Approval  11/8/2018 PASS
Plan Reviewer's activity  11/7/2018 PASS
Plan intake review approved
Intake Approval  11/2/2018 FAIL
(11-2-18) Refer to the circled items in the plan intake checklist. Resolve each item as directed. CJW
Application received  10/31/2018 DONE
Application submitted via PDS Online on Oct 31 2018 3:50PM
BLD-Concrete10/3/201910/4/2019 A 
DetailsDave Hannah
Ryan Phone #: ###-####
Routing PW Drainage11/9/2018   FAIL
DetailsBrian Murphy
NEED ACHD AGGREMENT80%TSS TREATMENT APDX J ECT
Routing PW Sewer Design1/23/2019   FAIL
Please submit sewer extension plans that are associated with the central plant and parking garage for review.