BLD-Blower Door Test Results | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | DONE |
Tell Riley
|
|
|
4.5 ACH 50 1761 CFM @ 50 pa
|
BLD-Final | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Tell Riley
|
|
|
|
DOC - Permit Finaled | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | FAIL |
Tell Riley
|
|
|
Chad-call for access code Phone #: ###-####//need blower door test completed//
|
BLD-Energy code compliance | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PASS |
Tell Riley
|
|
|
Chad Phone #: ###-####
|
BLD-Framing/Rough-in | 6/14/2019 | 6/19/2019 | 6/18/2019 | P | PASS |
Tell Riley
|
|
|
Bob Phone #: ###-####//framing approved per plans//ok to insulate only//
|
BLD-Wall Bracing | 6/6/2019 | 6/7/2019 | 6/7/2019 | A | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####
|
BLD-Foundation | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | CANC |
Jim Sly
|
|
|
Brian-call to meet-inspection request was for the wrong address so wants to be there since footings are poured Phone #: ###-####
|
BLD-Footing | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | PASS |
Jim Sly
|
|
|
Brian Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/1/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 4/29/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 4/12/2019 | 4/12/2019 | 4/29/2019 | | DONE |
|
|
|
04/25 sfd L1 Paper. 1st complete 4/19, wall bracing, 2nd bedroom window, waiting for fire
|
Routing - PLAN CHECK | 4/29/2019 | | 4/29/2019 | | PASS |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 4/29/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2019 | | DONE |
Jenny Nelson
|
|
|
|
Inspection Record Card- Bld | | | 4/29/2019 | | DONE |
|
|
|
|
Telephone call | | | 4/29/2019 | | DONE |
|
|
|
left a message for ryan informing this permit is ready to be picked up and the fee amount due
|
Permit Ready to Issue | | | 4/29/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/25/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 4/25/2019 | | DONE |
|
|
|
issued by mistake
|
Plan resubmittals received | | | 4/25/2019 | | DONE |
|
|
|
resubmittal received 2 sets of sheets A-2, A-3 & A-8-2 sets of res checks, took to Jenny
|
Routing - FIRE | 4/19/2019 | 4/19/2019 | 4/22/2019 | | PASS |
Lee G Meredith
|
|
|
05/03 8731 W Shellie residential fire review.
Fire flow availability report not provided, access distance exceeded.
4-22-2019 Note: Approved. Reference DOC_FIRE DEPT LETTER file in Record of Survey ROS18-00114 that eliminates the need for residential fire sprinklers for this building site.
|
Routing - MECHANICAL | 4/22/2019 | | 4/22/2019 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 4/22/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 4/18/2019 | | 4/19/2019 | | FAIL |
Jenny Nelson
|
|
|
Wall bracing deficiencies, bedroom window not on elev - need to know type for egress
|
Routing - PLANNING | 4/12/2019 | | 4/19/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - MECHANICAL | 4/12/2019 | | 4/18/2019 | | FAIL |
Troy James
|
|
|
emailed corrections to dustin mori
|
Routing - PUBLIC WORKS | 4/12/2019 | | 4/16/2019 | | PASS |
Morgan Webb
|
|
|
|
Route to Impact Fee Review | 4/12/2019 | 4/15/2019 | 4/15/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 4/12/2019 | | 4/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 4/12/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/12/2019 | | DONE |
|
|
|
|
Application received | | 4/12/2019 | | | |
|
|
|
|