Routing - PLAN CHECK | 8/13/2020 | | 8/13/2020 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 8/11/2020 | | 8/12/2020 | | PASS |
Carl Westfall
|
|
|
Plan intake review approved
|
Plan Modification Accepted | | | 8/11/2020 | | DONE |
|
|
|
3HR firewall and openings at parking garage. Fireblocking at corridior wall to ratain 1HR fire resistance rating
|
BLD-Foundation | 6/22/2020 | 6/24/2020 | 6/25/2020 | P | PEND |
Dave Hannah
|
|
|
Area D foundation. MTI is schedule for a Thursday am pour. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 5/5/2020 | 5/5/2020 | 5/6/2020 | P | PART |
Brandon Shaw
|
|
|
LEVEL 6 SUSPENDED SLAB POUR - POUR AREA A. EAST SHEAR WALL @ LEVEL 5. Pend Special inspection...
|
BLD-Concrete | 4/24/2020 | 4/24/2020 | 4/28/2020 | P | PEND |
Dave Hannah
|
|
|
10 columns @ level 5 area A (south west corner of level 5) Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 4/27/2020 | 4/27/2020 | 4/28/2020 | P | PEND |
Dave Hannah
|
|
|
SUSPENDED SLAB POUR - LEVEL 5 POUR AREA C; SHEAR WALL @ SOUTH SIDE OF LEVEL 5. POURING TOMORROW MORNING. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 4/17/2020 | 4/20/2020 | 4/21/2020 | P | PART |
Dave Hannah
|
|
|
PT deck level 5 pour 2. MTI is scheduled. 4 am Tuesday pour. Phone #: ###-#### Inspection requested via web by Jim Williams work i progress
|
BLD-Concrete | 4/17/2020 | 4/20/2020 | 4/21/2020 | A | PART |
Dave Hannah
|
|
|
Shear wall west elevation level 5-6 Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 4/13/2020 | 4/13/2020 | 4/14/2020 | P | PASS |
Dave Hannah
|
|
|
LEVEL 5 - POUR AREA A - PT DECK. COLUMNS @ EAST SIDE LEVEL 4-5 AND LEVEL 4 - NORTH SHEAR WALL. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Conference | 3/26/2020 | 3/27/2020 | 3/31/2020 | P | PART |
Dave Hannah
|
|
|
south shear wall and 10 columns pour B. MTI has been scheduled. Concrete scheduled for 10 am Monday Inspection requested via web by Jim Williams
|
BLD-Concrete | 3/23/2020 | 3/24/2020 | 3/25/2020 | P | PEND |
Dave Hannah
|
|
|
West shear wall reinforcement, 10 columns. suspended slab level 4 pour B. MTI is scheduled 4 am 3/25 concrete. Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inspection sign offs
|
BLD-Concrete | 3/19/2020 | 3/19/2020 | 3/19/2020 | P | PEND |
Dave Hannah
|
|
|
Columns and shear wall Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inspection sign offs
|
BLD-Concrete | 3/9/2020 | 3/10/2020 | 3/11/2020 | A | CANC |
Dave Hannah
|
|
|
LEVEL 3 - SOUTH SHEAR WALL; 10 COLUMNS LEVEL 3 POUR B AREA. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Concrete | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PEND |
Dave Hannah
|
|
|
SUSPENDED SLAB LEVEL 3 - AREA C Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 3/2/2020 | 3/3/2020 | 3/9/2020 | P | PASS |
Dave Hannah
|
|
|
LEVEL 3 - SUSPENDED SLAB - POUR B Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Concrete | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | CANC |
Dave Hannah
|
|
|
COLUMNS @ LEVEL 3 AREA A - FIRST POUR Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inpection sign off
|
BLD-Concrete | 2/27/2020 | 2/27/2020 | 2/28/2020 | A | PEND |
Dave Hannah
|
|
|
north shear wall, 2 columns at ramp Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 2/19/2020 | 2/25/2020 | 2/25/2020 | A | PEND |
Dave Hannah
|
|
|
PT slab Pour 1 level 3 Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inspection sign off
|
BLD-Concrete | 2/19/2020 | 2/20/2020 | 2/25/2020 | P | PEND |
Dave Hannah
|
|
|
Columns and shear wall parking garage east Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inspection sign off
|
BLD-Concrete | 2/12/2020 | 2/13/2020 | 2/19/2020 | A | PART |
Dave Hannah
|
|
|
10 columns and west concrete shear wall level 2-3 Phone #: ###-#### Inspection requested via web by Jim Williams
|
Print Occupancy Form | | | 11/5/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/5/2019 | | DONE |
|
|
|
|
Telephone call | | | 11/4/2019 | | DONE |
|
|
|
sent an email to kim informing this permit is expired and that she may send in a request for an extension
|
OVERRIDE | | | 10/31/2019 | | |
|
|
|
|
Plan assigned to (CJW) | 6/3/2019 | 7/12/2019 | 10/31/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 07/05/19 (New Building - 25 days) (eplan - 330 sheets) Park Place Garage Building (issue after footing permit)
|
Plan Reviewer's activity | | | 10/31/2019 | | PASS |
|
|
|
This permit was held up until after the footing and foundation permit was approved (BLD19-03918).
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2019 | | DONE |
|
|
|
MET WESTON@GARDNERCOMPANY.NET
**DO NOT ISSUE WITHOUT BLD19-01479**
NEED
RP
MET
GC Form
ACHD
Revised Value
|
Routing - PLANNING | 10/11/2019 | | 10/15/2019 | | PASS |
David Moser
|
|
|
|
Routing PW Street Lights | 10/11/2019 | | 10/14/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLAN CHECK | 10/11/2019 | | 10/14/2019 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 10/11/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/8/2019 | | DONE |
|
|
|
|
Routing - FIRE | 9/24/2019 | 9/24/2019 | 10/7/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 9/24/2019 | | 10/4/2019 | | PASS |
Carl Westfall
|
|
|
Jared Bauder (Jacobs - CH2MHill)
|
Routing - PLAN CHECK | 9/19/2019 | | 10/2/2019 | | PASS |
Carl Westfall
|
|
|
Pending Structural
|
Routing - Design Review | 9/24/2019 | | 10/2/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLUMBING | 9/24/2019 | | 9/30/2019 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC. See Redlines
|
Routing - MECHANICAL | 9/24/2019 | | 9/26/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Street Lights | 9/24/2019 | | 9/25/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLANNING | 9/24/2019 | | 9/24/2019 | | FAIL |
David Moser
|
|
|
need to provide access agreement with Parks for connection to greenbelt and Public Works approved Site Restoration Plan
|
Routing - PLAN CHECK | 9/19/2019 | | 9/24/2019 | | FAIL |
Carl Westfall
|
|
|
Delay in routing do to improperly uploaded drawings
|
Plan resubmittals received | | | 9/19/2019 | | DONE |
|
|
|
|
Routing - FIRE | 8/17/2019 | 8/17/2019 | 9/10/2019 | | FAIL |
Erika Akin
|
|
|
Attrached comments to case and emailed architect
|
Plan resubmittals requested | | | 9/10/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/17/2019 | | 9/5/2019 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (Jacobs - CH2MHill)
|
Plan Reviewer's activity | | | 9/4/2019 | | DONE |
|
|
|
Emailed the Structural Engineer Consultant asking about the status of the 2nd review. Also talked to Fire.
|
Routing - Design Review | 8/17/2019 | | 8/23/2019 | | FAIL |
Josh Wilson
|
|
|
DR Modification not yet approved (DRH19-00362)
|
Routing - Addressing | 8/17/2019 | | 8/21/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Drainage | 8/17/2019 | | 8/21/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 8/20/2019 | | 8/20/2019 | | FAIL |
Tom Marshall
|
|
|
Need a street light plan.
|
Routing - PLUMBING | 8/17/2019 | | 8/20/2019 | | FAIL |
Dan Ediger
|
|
|
Complete corrections acording to the ChangeMark
|
Routing - PLANNING | 8/17/2019 | | 8/20/2019 | | FAIL |
David Moser
|
|
|
Need access agreement with Parks and Rec and need Site Restoration Plan approved by Public Works and Parks & Rec
|
Routing - MECHANICAL | 8/17/2019 | | 8/19/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/14/2019 | | 8/17/2019 | | FAIL |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 8/14/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/27/2019 | 7/30/2019 | 7/30/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 6/3/2019 | 6/3/2019 | 7/11/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 6/3/2019 | | 7/11/2019 | | FAIL |
Carl Westfall
|
|
|
Park Place Apartments - Garage
|
1st review completed | | | 7/11/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/11/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/3/2019 | | 6/14/2019 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (Jacobs - CH2MHill)
|
Routing PW Drainage | 6/4/2019 | | 6/11/2019 | | FAIL |
Brian Murphy
|
|
|
CAN BE PASSED BUT NEED TO PASS GRADING PLAN FIRST
|
Routing PW Flood Plain | 6/4/2019 | | 6/10/2019 | | PASS |
Jason C. Taylor
|
|
|
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 6/3/2019 | | 6/6/2019 | | FAIL |
Troy James
|
|
|
See eplan
|
Routing - PLUMBING | 6/3/2019 | | 6/5/2019 | | FAIL |
Dan Ediger
|
|
|
Sizing per ISPC
|
Routing - PLANNING | 6/3/2019 | | 6/5/2019 | | FAIL |
David Moser
|
|
|
need to provide access agreement with Parks for connection to greenbelt and Public Works approved Site Restoration Plan
|
Routing - Addressing | 6/3/2019 | | 6/5/2019 | | FAIL |
Doug Chausow
|
|
|
Provide separate floor plans for floors 4 and 5 (currently combined onto one sheet) with unit numbers.
|
Routing PW Street Lights | 6/4/2019 | | 6/5/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - Erosion and Sediment | 6/3/2019 | | 6/5/2019 | | PASS |
Michael Zawacki
|
|
|
Please refer to ESC19-00542 issued with grading permit as main site permit.
|
Routing PW Solid Waste | 6/4/2019 | | 6/5/2019 | | PASS |
Peter J. McCullough
|
|
|
SW containers to be moved by building staff to designated location
|
Routing PW Sewer Design | 6/4/2019 | | 6/4/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2019 | | 6/4/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 6/3/2019 | | PASS |
Carl Westfall
|
|
|
Prescreen approved/fees paid 6-3-19
|
Routing - Design Review | 6/3/2019 | | 6/3/2019 | | FAIL |
Josh Wilson
|
|
|
See changemarks on multiple sheets. Elevations do not match those approved with DRH19-00093. Submit a Design Review modification.
|
Plan Reviewer's activity | | | 5/31/2019 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 5/14/2019 | | FAIL |
|
|
|
(5-14-19) Refer to the circled items in the plan intake checklist. Resolve each item as directed. CJW
|
Intake Approval | | | 5/6/2019 | | FAIL |
|
|
|
M and P sheets not oriented properly. They were deleted. Completely filled out plan intake checklist 502 required.
|
Application received | | | 4/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 30 2019 4:24PM
|
Plan assigned to (CJW) | 8/11/2020 | 8/11/2020 | | | |
Carl Westfall
|
|
|
plan mod - Park place apartments (routed to staff)
|