Print Statement | | | 11/14/2019 | | DONE |
|
|
|
|
Print Statement | | | 10/30/2019 | | DONE |
|
|
|
|
Zoning Approval | 10/29/2019 | 10/29/2019 | 10/29/2019 | | DONE |
Katelyn Menuge
|
|
|
Carports no inspection required
|
Print Occupancy Form | | | 10/29/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/29/2019 | | DONE |
|
|
|
|
First Notice | 8/27/2019 | 8/27/2019 | 9/19/2019 | | DONE |
Jim Storey
|
|
|
mailed 9-20-19
|
BLD-Final | 8/26/2019 | 8/27/2019 | 8/27/2019 | P | PASS |
Jim Storey
|
|
|
call rob Phone #: ###-#### Inspection requested via web by J.C. Murray final ok
|
DOC - Permit Finaled | 8/27/2019 | 8/27/2019 | 8/27/2019 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 8/26/2019 | 8/27/2019 | 8/27/2019 | A | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, final life fire safety inspection for scope of work complete.
call rob Phone #: ###-#### Inspection requested via web by J.C. Murray
|
FIRE-Final Inspection | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | FAIL |
Troy Cobbley
|
|
|
No approved plans or small documents on site. I did spot check for the min. 26' clearance in several locations which they met. call on arrival Phone #: ###-#### Inspection requested via web by J.C. Murray
|
Print Occupancy Form | | | 5/23/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/23/2019 | | DONE |
|
|
|
|
1st review completed | | | 5/21/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 5/21/2019 | | DONE |
|
|
|
all met: bblack@petrainc.net
NEED
RP
GC FORM
REVISED VALUE
|
Routing Off Site - STRUCTURAL | 5/7/2019 | | 5/21/2019 | | PASS |
Michael Hanson
|
|
|
Passed per approval in ePlan by AHJ.
|
Plan assigned to (M_H) | 5/7/2019 | | 5/21/2019 | | DONE |
Michael Hanson
|
|
|
06/17 #502 ePlan - Skyline Apts Carports
|
Routing - PLAN CHECK | 5/7/2019 | | 5/21/2019 | | PASS |
Michael Hanson
|
|
|
|
Routing - FIRE | 5/6/2019 | 5/7/2019 | 5/20/2019 | | PASS |
Erika Akin
|
|
|
No comments attached. U occupancy. Carports do not impact required 26 foot FD access throughout the site. Inspector to field verify no encroachment.
|
Routing - Addressing | 5/7/2019 | | 5/9/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLANNING | 5/7/2019 | | 5/8/2019 | | PASS |
Brent Moore
|
|
|
|
Routing - Design Review | 5/7/2019 | | 5/8/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PUBLIC WORKS | 5/7/2019 | | 5/7/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 5/7/2019 | | 5/7/2019 | | PASS |
Michael Zawacki
|
|
|
Please refer to ESC17-01754 for site inspections.
|
Intake Approval | | | 5/7/2019 | | PASS |
Carl Westfall
|
|
|
Prescreen approved/fees paid 05/06/19
|
Routing PW Drainage | 5/7/2019 | | 5/7/2019 | | PASS |
Brian Murphy
|
|
|
|
Plan Reviewer's activity | | | 5/6/2019 | | PASS |
|
|
|
Plan intake review approved
|
Application received | | | 5/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 3 2019 3:00PM
|