BLD-Final | 7/6/2020 | 7/6/2020 | 7/6/2020 | P | PART |
Tell Riley
|
|
|
Kyle Phone #: ###-####//project appears to be completed per the drawing and scope//railings/guards installed in locations required on plans//need special inspection report for complete final//
|
PubWorks Occupancy Approval | 7/2/2020 | 7/2/2020 | 7/2/2020 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 6/17/2020 | 6/17/2020 | 6/17/2020 | | DONE |
Leon Letson
|
|
|
|
OVERRIDE | | | 9/24/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/24/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/24/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/24/2019 | | DONE |
|
|
|
all met and emailed otto@mcmjac.com CAN NEED
RP-met
GC FORM-met
REVISED VALUE-met
|
Plan assigned to (CDM) | 8/2/2019 | 8/2/2019 | 9/23/2019 | | PASS |
Carl D Madsen
|
|
|
09/12 (Resub) 09/06 Albertson Park L-3
|
Routing Off Site - STRUCTURAL | 9/16/2019 | | 9/23/2019 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/4/2019 | | 9/10/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 9/4/2019 | | 9/10/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 9/4/2019 | | DONE |
Joe Bruce
|
|
|
Plans receied in ePlan. **JHB**
|
Route to Impact Fee Review | 8/26/2019 | 8/29/2019 | 8/27/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/2/2019 | 8/2/2019 | 8/26/2019 | | PASS |
Erika Akin
|
|
|
No comments attached. No structures contrusted under this permit. No change to exisitng FD access.
|
1st review completed | | | 8/26/2019 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/2/2019 | | 8/24/2019 | | FAIL |
Carl D Madsen
|
|
|
KPFF
|
Routing - PLAN CHECK | 8/2/2019 | | 8/24/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 8/2/2019 | | 8/22/2019 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Flood Plain | 8/5/2019 | | 8/21/2019 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - Erosion and Sediment | 8/2/2019 | | 8/6/2019 | | PASS |
Andy J. Long
|
|
|
see also ESC19-00106 for KAP improvement. Site preparation inspection is required.
|
Routing - PLANNING | 8/2/2019 | | 8/5/2019 | | PASS |
Brent Moore
|
|
|
|
Routing - Addressing | 8/2/2019 | | 8/5/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Street Lights | 8/2/2019 | | 8/5/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PUBLIC WORKS | 8/2/2019 | | 8/2/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 7/30/2019 | | |
|
|
|
|
Intake Approval | | | 7/24/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide the following in order for your Prescreen to be approved:
1. The C, ESC, S and SP Drawing Sheets did not provide the required space and location on the Drawing for the City Approval Stamp. Please revise your Title Block as needed.
2. C001, C100 thru C114, G001, G002, G003, G004, GC001, GC002, EC001, EC002, EC003 are noted as "NOT FOR CONSTRUCTION" in the Title Block. Please remove and resubmit drawings.
3. Please verify the Land Use Zone designation on G001. It is Noted as “Open Space”.
4. I could not locate Sheet GS01. Upload Sheet GS01 that contains the Code Analysis and Building Data.
|
Application received | | | 7/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2019 12:08PM
|