BLD-Final | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | PASS |
Jim Storey
|
|
|
jason Phone #: ###-####
|
DOC - Permit Finaled | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####
|
BLD-Energy code compliance | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | NR |
Tony Young
|
|
|
Jason Phone #: ###-####// insulators just are starting,, will come back later in pm
|
BLD-Energy code compliance | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | NR |
Tony Young
|
|
|
Jason Phone #: ###-####,, needs insulation under stair area
|
BLD-Framing/Rough-in | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####
|
BLD-Framing/Rough-in | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Tony Young
|
|
|
Jason; Phone #: ###-####
|
BLD-Framing/Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PART |
Tony Young
|
|
|
Jason Phone #: ###-####,, strap plates x4,, rafters above stairs need to oppose each other,, and be suppoerted fully,, justify roof venting,, fire blocking with insulation ok,, ok to insulate if needed
|
OVERRIDE | | | 12/5/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 12/5/2019 | | 12/5/2019 | | PASS |
Josh Bogle
|
|
|
min Plan Review fee
|
Case Summary (BLD) | | | 12/5/2019 | | DONE |
Josh Bogle
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/5/2019 | | DONE |
|
|
|
plan mod
|
Inspection Record Card- Bld | | | 12/5/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/5/2019 | | DONE |
|
|
|
plan mod
|
BLD-Wall Bracing | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Josh Benart,, exterior ok after minor fixes
|
BLD-Footing | 8/28/2019 | 8/29/2019 | 8/29/2019 | P | PART |
Tony Young
|
|
|
Pat Phone #: ###-####.. work in progress
|
OVERRIDE | | | 8/22/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 8/22/2019 | 8/22/2019 | 8/22/2019 | A | DONE |
Josh Bogle
|
|
|
bringing additional paper work
|
Plan assigned to (JAB) Josh | 8/9/2019 | 8/9/2019 | 8/22/2019 | | PASS |
Josh Bogle
|
|
|
08/15 addition, paper - 1st done
|
Routing - PLAN CHECK | 8/22/2019 | | 8/22/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 8/22/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 8/22/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 8/22/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/22/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/12/2019 | | 8/13/2019 | | FAIL |
Josh Bogle
|
|
|
structure doesn't pencil - gave a marked up plan back to applicant for revision
|
1st review completed | | | 8/13/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 8/9/2019 | | 8/12/2019 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (Zoning) | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | PASS |
Josh Bogle
|
|
|
took in as level two - routed to Mechanical
|
Application received | | 8/9/2019 | | | |
|
|
|
|