Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberBLD19-03649
StatusFinaled
Name BRAD SMITH
Site Address 12601 W EXPLORER DR Unit: 100
Project NameAmericor
Customer Number 
ePlanReviewNo
Description
**(AMERICOR) ** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for a 5,134 sq. f.t existing Office tenant. This space was previously a Vanilla space under BLD19-01372 and BLD19-01272. NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT. There will be no change to the occupancy. **BJM**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  9/30/2019 DONE
BLD-Final9/26/20199/27/20199/27/2019APASS
DetailsTell Riley
Adam Phone #: ###-####//no changes to existing//
FIRE-Final Inspection9/26/20199/26/20199/26/2019PPASS
DetailsTroy Cobbley
Life safety passed. Adam Phone #: ###-####
BLD-Final9/23/20199/24/20199/24/2019ANR
DetailsTell Riley
Adam Phone #: ###-####//needs final on fire life safety//
FIRE-Final Inspection9/23/20199/23/20199/23/2019PFAIL
DetailsTroy Cobbley
Repair the exit sign over the main exit and repair all emergency lights. Also provide a fire extinguisher as discussed. Adam Phone #: ###-####
Issue PAID IN FULL permit  9/23/2019 DONE
Plan assigned to (BJM)9/16/20199/16/20199/20/2019 DONE
DetailsBrian McGowan
09/25- Occupancy
Routing - PLAN CHECK9/16/2019 9/20/2019 PASS
DetailsBrian McGowan
1st review completed  9/20/2019 DONE
DetailsBrian McGowan
Case Summary (BLD)  9/20/2019 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  9/20/2019 DONE
DetailsBrian McGowan
Print Occupancy Form  9/20/2019 DONE
Print Occupancy Form  9/20/2019 DONE
Permit Ready to Issue  9/20/2019 DONE
met
Telephone call  9/20/2019 DONE
Left voicemail for Brad to inform him the permit is ready to pick up.
Routing - PUBLIC WORKS9/16/2019 9/18/2019 PASS
DetailsMorgan Webb
Routing - Addressing9/16/2019 9/17/2019 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  9/16/2019 DONE
Intake Approval  9/16/2019 PASS
Recd Pcfee & Taken To Pln CK  9/16/2019 DONE
First Notice 10/10/2019   
Application received 9/16/2019