Permit Information
Permit NumberBLD19-04893
StatusIssued
Name BEST BUY REAL ESTATE LLC
Site Address 10548 W BUSINESSPARK LN
Project NameSouthwind busine. park Bldg. F
Customer Number 
ePlanReviewYes
Description
(SOUTHWIND BUSINESS PARK - BUILDING F - VANILLA T.I.) NO OCCUPANCY ALLOWED UNDER THIS PERMIT. TENANT SHALL APPLY FOR CERTIFICATE OF OCCUPANCY PRIOR TO OCCUPYING THE SPACE. Permit is for the initial build out of a 1,840 sqft shell building created under BLD06-00170. Work to include: construction of a 1-hour rated non-bearing demising wall, interior non-bearing walls, doors, millwork, and interior finishes in compliance with chapter 8 of the 2015 IBC. This building is not fire sprinkled. This building shares a zero lot line with office building E. Approval is contingent upon adhering to the approved plans on file. **MDH**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan Reviewer's activity  7/7/2020 DONE
DetailsMichael Hanson
Spoke with Mike Jordan and he stated he had advised the contractor on the laydown parapet requirements for 4 feet from each side of the 2 hour demising wall.
BLD-Framing/Rough-in7/6/20207/6/20207/6/2020PPART
DetailsMike Jordan
Muhamed - Call for access 15 minutes prior if possible to allow travel time. Phone #: ###-####. Needs to complete airseal package and provide firecaulking in penetrations 4ft. from 2hr.firewall.
BLD-Framing/Rough-in7/2/20207/2/20207/2/2020PNH
DetailsMike Jordan
Muhamed - *Screened* Phone #: ###-####. Doors locked, no access. Also noted that the airseal pak needs to be completed prior to framing inspection.
Place hold on job4/10/2020 4/16/2020 DONE
DetailsGabe Brenner
waiting for signed permit
Issue PAID IN FULL permit  4/9/2020 DONE
Inspection Record Card- Bld  4/9/2020 DONE
Route to Impact Fee Review1/17/20201/20/20201/17/2020 PASS
DetailsTravis P Black
Review requested for Commercial Permit
1st review completed  1/17/2020 FAIL
DetailsMichael Hanson
Routing - PLAN CHECK1/17/2020 1/17/2020 PASS
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  1/17/2020 DONE
DetailsMichael Hanson
Permit Ready to Issue  1/17/2020 DONE
MET

Updated Revised Certificate of Value

MET
GC Form
Plan assigned to (M_H)12/24/2019 1/17/2020 DONE
DetailsMichael Hanson
1st review completed - 01/17 #520 L3 ePlan - Vanilla T.I
Routing - FIRE12/24/201912/24/20191/15/2020 PASS
DetailsErika Akin
No comments attached. Vanilla TI in exisitng shell.
Routing - PLAN CHECK12/24/2019 1/15/2020 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required.
Routing - PUBLIC WORKS12/24/2019 12/31/2019 PASS
DetailsMorgan Webb
Routing - PLANNING12/24/2019 12/30/2019 PASS
DetailsEthan Mansfield
No Exterior Work allowed
Routing - Addressing12/24/2019 12/27/2019 PASS
DetailsDoug Chausow
Routing - MECHANICAL12/24/2019 12/27/2019 PASS
DetailsTroy James
Routing - PLUMBING12/24/2019 12/27/2019 PASS
DetailsDan Ediger
Per Plans and ISPC
Intake Approval  12/23/2019 FAIL
DetailsMichael Hanson
Provide location of portable fire extinguisher.
Intake Approval  12/23/2019 PASS
Application received  12/18/2019 DONE
Application submitted via PDS Online on Dec 18 2019 2:46PM