Final | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McCarrel C-4 gibbons exhibit final ok
|
Final | 2/27/2019 | 2/28/2019 | 2/28/2019 | A | PART |
Rock A. Hudson
|
|
|
Final for gibbon building Phone #: ###-#### Inspection requested via web by Mike McCarrel To install GFCI devices protecting soffit receptacles in a readily accessible location by final as per 210.8. General contractor must provide build up of grade in front of panel location ASAP as per 240.24(A). TCO of building C4 ok
|
Rough-In Permanent Service | 1/23/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Rock A. Hudson
|
|
|
inspect service to energize Phone #: ###-#### Inspection requested via web by Mike McCarrel 6011 AIC on a 10k rated main south west service on C-4 building. p/s u/g n ok
|
Electrical Rough-In | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PASS |
Rock A. Hudson
|
|
|
Inspect walls for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud Building C-4 gibbens exibit wall and soffit rough in ok cover
|
Electrical Rough-In | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | PASS |
Rock A. Hudson
|
|
|
Please call Mike Clover Phone #: ###-#### Inspection requested via web by Kevin Perez Concrete encased electrode rough in ok cover
|
Issue PAID IN FULL permit | | | 7/19/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/19/2018 | | DONE |
|
|
|
This permit was created on the web by Kevin Perez
|
First Notice | 6/6/2019 | 6/6/2019 | | | |
Rock A. Hudson
|
|
|
|