Electrical Rough-In | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PASS |
Tom Saunders
|
|
|
Wall cover Phase 5 Contact Lance 208.703.2035 to get in space Phone #: ###-#### Inspection requested via web by David Feller... switch and 3 receptacles new hallway from outside door
|
Electrical Rough-In | 7/16/2020 | 7/17/2020 | 7/20/2020 | P | PASS |
Tom Saunders
|
|
|
ceilings restrooms and phase 5 call lance 30 minutes before arrival for access 208 703 2035 Phone #: ###-#### Inspection requested via web by David Feller...ok to cover
|
Electrical Rough-In | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | PASS |
Tom Saunders
|
|
|
Phase 4 wall cover wall rough in. Contact Lance ###-#### Phone #: ###-#### Inspection requested via web by David Feller...new affice walls x 2 ...phase 4...ok to cover
|
Electrical Rough-In | 6/9/2020 | 6/10/2020 | 6/10/2020 | A | PASS |
Tom Saunders
|
|
|
Wall rough in Phase 5. Contact Lance ###-#### Phone #: ###-#### Inspection requested via web by David Feller...ok to cover walls phase 5 and bathroom walls phase 4
|
Electrical Rough-In | 4/28/2020 | 4/29/2020 | 4/29/2020 | A | PASS |
Tom Saunders
|
|
|
Wall rough in Phase 5. Phone #: ###-#### Inspection requested via web by David Feller... walls ok to cover...8 outlets and switching for new rm...storage rm for material of next phases
|
Electrical Rough-In | 4/8/2020 | 4/9/2020 | 4/9/2020 | A | PASS |
Tom Saunders
|
|
|
Phase 4 wall rough in Phone #: ###-#### Inspection requested via web by David Feller... new hallway wall 4 recps, 1 switch and 2 data
|
Electrical Rough-In | 3/9/2020 | 3/10/2020 | 3/10/2020 | A | PASS |
Eric Story
|
|
|
Wall rough in call Lance 208 703 2035 Phone #: ###-#### Inspection requested via web by David Feller Walls in phase 3-A and 4 ok to cover
|
Electrical Rough-In | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | PASS |
Tom Saunders
|
|
|
walls phase 3 Phone #: ###-#### Inspection requested via web by David Feller... ok to cover 2 outlets short wall
|
Final | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PART |
Tom Saunders
|
|
|
Partial final Phase 2 Phone #: ###-#### Inspection requested via web by David Feller... Phase 2 of total project...new cubicle/work stations and breakroom...partial final for area
|
Electrical Rough-In | 1/22/2020 | 1/23/2020 | 1/23/2020 | A | PASS |
Tom Saunders
|
|
|
Ceiling cover contact Lance 208.703.2035 Phone #: ###-#### Inspection requested via web by David Feller... grid ok to cover-areas opened for new walls and hallway, the rest is existing not changed
ok to cover new walls(4 outlets)...phase 3 of job
|
Electrical Rough-In | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | PASS |
Tom Saunders
|
|
|
Wall cover inspection
contact Lance for access to site 208 703 2035 Phone #: ###-#### Inspection requested via web by David Feller... phase 2 ...new walls creating offices, breakroom, and area for call center cubicles...no conference rm
|
Issue PAID IN FULL permit | | | 12/27/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/27/2019 | | DONE |
|
|
|
This permit was created on the web by David Feller
|