Random Inspection | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | PASS |
Andy J. Long
|
|
|
First phase of project covered under this permit is complete. New grading and building permits have been issued, ESC covered under ESC17-01132. Beniton is operator and same RP Chase is on duty.
|
DOC - Permit Finaled | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 11/6/2017 | 11/6/2017 | 11/6/2017 | P | PASS |
Michael Zawacki
|
|
|
Perimeter controls intact. Buffer left around White Water Park Blvd. Entrance in use, some trackout but was swept up. Working on grading and installing utilities.
|
Site Final | 10/13/2017 | 10/13/2017 | 10/13/2017 | P | PEND |
Michael Zawacki
|
|
|
Site prep and walkthrough. Permit to be issued Tuesday.
|
Site Preparation | 8/7/2017 | 8/7/2017 | 8/9/2017 | P | PASS |
Andy J. Long
|
|
|
|
Routing - Erosion and Sediment | 7/28/2017 | | 7/31/2017 | | DONE |
Andy J. Long
|
|
|
ESC general permit issued. Valid RP designated.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2017 | | DONE |
Andy J. Long
|
|
|
|
Permit Ready to Issue | | | 7/31/2017 | | DONE |
|
|
|
|
Telephone call | | | 7/31/2017 | | DONE |
|
|
|
Spoke with Chase informing him this permit is ready and the fee amount due for issuance
|
Issue & PRINT permit COM | | | 7/31/2017 | | DONE |
|
|
|
|
Application received | | | 7/28/2017 | | |
|
|
|
|