Site Final | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | PASS |
Andy J. Long
|
|
|
Bathroom installed. Rest of bike park/dog park to be monitored under ESC18-01687
|
Fees Due Hold | 4/27/2019 | | 9/13/2019 | | DONE |
Tisha Gallop
|
|
|
|
General Inspection | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 7/25/2019 | 7/25/2019 | 7/26/2019 | P | PASS |
Michael Zawacki
|
|
|
WIP on all sites. Multiple water trucks on site, no dust. Construction entrance installed.
|
Issue & PRINT to be Invoiced | | | 4/26/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/3/2019 | | 4/3/2019 | | DONE |
Michael Zawacki
|
|
|
|
Application received | | | 3/1/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 1 2019 4:30PM
|