INSP-Final Inspection | 3/26/2014 | 3/27/2014 | 3/27/2014 | A | PASS |
Forrest France
|
|
|
Correction items per previous inspection verified for completion. Scope of work finished, walkthrough passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 3/26/2014 | 3/26/2014 | 3/26/2014 | P | PART |
Forrest France
|
|
|
Final pending C/N items per C. Hansen.
|
INSP-Sprinkler Rough-in | 1/7/2014 | 1/8/2014 | 1/8/2014 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler system modifications per the scope of permit work are complete. Final pending verification of spacing once partition walls are built per plan.
|
Inspection Record Card- Fire | 12/5/2013 | | 12/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Sprinkler Plan Check | 12/5/2013 | | 12/5/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/5/2013 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/5/2013 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 12/4/2013 | | 12/4/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/4/2013 | | 12/4/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 12/4/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/4/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 11/25/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 25 2013 1:29PM
|
Inspection Record Card- Fire | 12/5/2013 | | | | |
|
|
|
|