INSP-Final Inspection | 2/11/2019 | 2/12/2019 | 2/12/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Please call 30 minutes prior to arrival so we can let you into the space Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 2/12/2019 | 2/12/2019 | 2/12/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, hard lid in restroom approved for cover.
|
Issue and Print Permit | | | 1/28/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/25/2019 | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/25/2019 | | 1/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/25/2019 | | DONE |
|
|
|
met
|
Application received | | | 1/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 18 2019 4:32PM
|