INSP-Final Inspection | 2/26/2019 | 2/26/2019 | 2/26/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 2/26/2019 | 2/26/2019 | 2/26/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | FAIL |
Jim Page
|
|
|
Cover is not approved, tenant space has numerous where insulation is hanging below hanging material, one area noticed has the insulation on the upright head. Insulation needs to be secure and above deflector before cover can be approved.
Cover Inspection. Terry Nelson Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
Permit Ready to Issue | | | 2/22/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/22/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/21/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/21/2019 | | 2/21/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/21/2019 | | 2/21/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 2/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 15 2019 3:10PM
|
Intake Approval | | | 2/15/2019 | | FAIL |
Mark Stumbaugh
|
|
|
No BLD permit issued for this project. Under review BLD19-00180
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|