INSP-Supply line flush | 5/19/2020 | 5/20/2020 | 5/20/2020 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
This an early inspection at 6:00AM for a flush.Please contact Troy Nelson. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
Fees Due Hold | 5/13/2020 | | 5/15/2020 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply has been witnessed, no pressure loss observed at riser provided gauge.
|
INSP-Supply line flush | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | CANC |
Jim Page
|
|
|
Request was for an underground hydro, not a flush, this request is cancelled.
Please colntact Troy Nelson for inspection Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 10/16/2019 | 10/17/2019 | 10/17/2019 | P | PART |
Troy Cobbley
|
|
|
*** PASS Partial underground. Area inspected is marked on stamped plans. OK to cover inspected area only. MAS***
This inspection is for cover for underground piping. Troy Nelson will call when ready. Phone #: ###-#### >> Inspection requested via web by Daniel Buccino
|
Issue and Print Permit | | | 9/10/2019 | | DONE |
|
|
|
|
Application received | | | 9/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 6 2019 10:19AM
|
Intake Approval | | | 9/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/6/2019 | | 9/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/6/2019 | | 9/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 9/6/2019 | | DONE |
|
|
|
met
|