INSP-Sprinkler Rough-in/Hydro | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Troy Cobbley
|
|
|
Hydro test witnessed with no visual pressure loss. Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/13/2020 | 5/13/2020 | 5/13/2020 | P | FAIL |
Troy Cobbley
|
|
|
Tower 1, left riser/north overhead hydro failed due to visible loss on the guage. The righ hand riser passed. Call James before heading out! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2020 | 5/12/2020 | 5/13/2020 | A | FAIL |
Troy Cobbley
|
|
|
Tower 1, left riser/north overhead hydro failed due to visible loss on the guage. The righ hand riser passed. Call James before heading out! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2020 | 5/11/2020 | 5/11/2020 | A | FAIL |
Troy Cobbley
|
|
|
Contact could not meet at the same time I could. Will need to be rescheduled. Overhead hydro, call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 4/9/2020 | 4/9/2020 | 4/9/2020 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered. Re-inspection, as built is approved, FDC relocated. Please call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
CHANGE STATUS TO (ISS) | | | 4/9/2020 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 4/7/2020 | | 4/8/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
Sprinkler Plan Check | 4/8/2020 | | 4/8/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 2 hr
No new devices
|
Permit Ready to Issue | | | 4/8/2020 | | DONE |
|
|
|
**PLAN MOD - DO NOT RE-ISSUE**
|
Plan Modification Accepted | | | 4/7/2020 | | DONE |
|
|
|
Work Flow requested to be opened for a plan mod
|
INSP-Sprinkler Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | FAIL |
Troy Cobbley
|
|
|
Provide plan mods indicating the actual pipe routing. Repair tenting. It appears the FDC needs to be relocated to the street side of the building. It is currently on the west side in the yard/land scaping.
Call James before heading out, rough and tenting inspection. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 11/12/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/29/2019 | | 11/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 11/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 11/5/2019 | | DONE |
|
|
|
met
|
Application received | | | 10/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2019 11:47AM
|
Intake Approval | | | 10/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 10/29/2019 | | 10/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|