INSP-Final Inspection | 7/6/2020 | 7/6/2020 | 7/6/2020 | P | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, final fire alarm inspection is complete.
This is for the fire alarm permit. The Paint Booth Interlock has been modified to shutdown the conveyor and heat tunnel. Phone #: ###-#### Inspection requested via web by Jason Heath
|
INSP-Final Inspection | 6/30/2020 | 7/2/2020 | 7/2/2020 | A | FAIL |
Jim Page
|
|
|
Conveyor line did not shut down on fire alarm activation as stated in building permit fire code review comments.
I am trying to get Rick from TVFP at the same time as my FINAL. Please call me early as possible on Thursday so I can get Rick from TVFP on board Phone #: ###-#### Inspection requested via web by Jason Heath
|
Issue and Print Permit | | | 6/18/2020 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 6/17/2020 | | 6/17/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 6/17/2020 | | PASS |
|
|
|
|
1st review completed | | | 6/17/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 6/17/2020 | | 6/17/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/17/2020 | | DONE |
|
|
|
Passed with review comments.
|
Permit Ready to Issue | | | 6/17/2020 | | DONE |
|
|
|
|
Application received | | | 6/9/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 9 2020 2:50PM
|