Final | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Jack Reynolds
|
|
|
Final mechanical Phone #: ###-#### Inspection requested via web by Cesar Rodriguez - final ok
|
Final | 10/28/2019 | 10/28/2019 | 10/28/2019 | P | FAIL |
Jack Reynolds
|
|
|
Final mech, please ring door bell, builder stated she would be there, thanks Phone #: ###-#### Inspection requested via web by Cesar Rodriguez - A/C needs locking caps installed on service ports
|
Final | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | FAIL |
Jack Reynolds
|
|
|
Final mechanical Phone #: ###-#### Inspection requested via web by Cesar Rodriguez - line set needs uv protection installed - line penetrations needs sealed - A/C needs locking caps installed on service ports
|
Mec-Aging Inspection | 9/4/2019 | 9/4/2019 | 9/4/2019 | | DONE |
Jack Reynolds
|
|
|
WIP
|
Rough-in | 2/15/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Jack Reynolds
|
|
|
Pressure witness and rough in, thanks Phone #: ###-#### Inspection requested via web by Cesar Rodriguez - R/I ok
|
Pressure Test | 2/15/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Jack Reynolds
|
|
|
Pressure witness and rough in, thanks Phone #: ###-#### Inspection requested via web by Cesar Rodriguez - 20lb gas pressure test -5lb flue pressure test ok - tagged meter location
|
Issue PAID IN FULL permit | | | 1/23/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/23/2019 | | DONE |
|
|
|
This permit was created on the web by Cesar Rodriguez
|